# Ground-Up Construction Loan Draw Schedule Explained

Published September 1, 2026

By [Jason Taken](https://jakenfinancegroup.com/jason-taken/) · Principal

Learn how investor construction draws move from completed work to inspection and payment. Budget reimbursement timing, contractor cash and loan interest.

Construction draws release funds after **third-party inspection** at milestones — typically **8–12 draws** on a 12-month build. Interest often accrues on the **full loan commitment**, including undrawn holdback.

Submit clean draw packages early. [How to submit a scope of work](/guides/how-to-submit-a-scope-of-work/) · [new construction loans](/new-construction-loans-for-investors/).

## Typical draw milestones — 12-month SFR build

| Draw # | Milestone | % of budget |
| --- | --- | --- |
| 1 | Foundation / footings | 10–15% |
| 2 | Framing / roof dry-in | 20–25% |
| 3 | Plumbing / electrical rough | 15–20% |
| 4 | HVAC / insulation | 10% |
| 5 | Drywall | 10% |
| 6 | Cabinets / trim | 10% |
| 7 | Final MEP / fixtures | 10% |
| 8 | CO / punch list | 5–10% |

Each draw requires **third-party inspection** — submit invoices, lien waivers, and photos **48 hours before** inspection date.

## Common draw delays — and fixes

| Delay | Fix |
| --- | --- |
| Incomplete lien waivers | Collect from subs at each draw |
| Work ahead of schedule | Lender won’t fund uninspected work |
| GC idle between draws | Stagger subs; pre-order long-lead items |
| Change orders without approval | Submit CO to lender before work |

Jaken Finance Group construction: **8.99%–13.5%** IO, **up to 100% LTC** qualified, **75% LTARV**. [How to submit SOW](/guides/how-to-submit-a-scope-of-work/) · [new construction hub](/new-construction-loans-for-investors/)

## Interest on undrawn balance — budget example

**$420K commitment, 12-month build, 10.75% IO**

| Month | Drawn | Undrawn | IO charge base (full commitment) |
| --- | --- | --- | --- |
| 1 | $63K | $357K | $420K → ~$3,763/mo |
| 6 | $252K | $168K | $420K → ~$3,763/mo |
| 12 | $420K | $0 | $420K → ~$3,763/mo |

You pay on **full commitment** even when undrawn — verify on term sheet from Jaken Finance Group.

## GC coordination for smooth draws

1.  Submit draw request **5 days before** needed wire
2.  Include **signed lien waivers** from all subs paid prior draw
3.  Schedule inspection **before** ordering next material batch
4.  Never get more than **one draw ahead** of inspected work

[Spec home financing](/blog/how-to-finance-a-spec-home-build-as-an-investor/) · [SOW submission](/guides/how-to-submit-a-scope-of-work/)

## Lien waiver chain — non-negotiable

Every draw package needs **unconditional lien waivers** from:

-   General contractor
-   Every subcontractor paid from prior draw
-   Material suppliers above state threshold

Missing waivers delay draws **5–10 business days** — you still pay IO on full commitment.

## Change orders during construction

| CO size | Lender process |
| --- | --- |
| Under 5% of budget | Often approved in-house |
| 5%–15% | Revised budget + re-inspection |
| Over 15% | Full re-underwrite of LTARV |

[Construction cost guide](/how-much-does-a-construction-loan-cost-for-investors/) · Jaken Finance Group **8.99%–13.5%** IO

## Retainage — why the final draw is never 100%

Most construction lenders hold **5%–10% retainage** until punch list completion and lien waiver clearance:

| Retainage % | On $420K budget | Release trigger |
| --- | --- | --- |
| 5% | $21,000 | Final inspection + CO |
| 10% | $42,000 | Same + 30-day lien period |

Sponsors who model eight equal draws forget retainage — and run out of cash for **landscaping, driveway, and final MEP** when the lender will not fund draw 8 at 100%. Budget sponsor cash for retainage gap plus 2 weeks of GC overhead after CO.

## Weather and force majeure — draw timing in cold climates

Chicago, DC, and Midwest builds lose **30–60 days** to frost, concrete cure delays, and roofing temperature minimums:

| Season | Risk | Draw impact |
| --- | --- | --- |
| Nov–Mar (cold) | Concrete/foundation delay | Draw 1–2 slip 3–6 weeks |
| Apr–May | Catch-up framing | Draw 2–3 compressed |
| Summer | On schedule | Normal cadence |

Extend your construction term sheet for **one free extension** if breaking ground after October 1 in the Midwest — IO on full commitment continues during weather delays whether or not the GC is on site. [Spec home financing](/blog/how-to-finance-a-spec-home-build-as-an-investor/) covers market selection; this section covers calendar risk on the same product.

## Inspector selection — who signs off on each draw

Construction lenders use **third-party inspectors** independent of the GC:

| Inspector type | What they verify | Typical fee |
| --- | --- | --- |
| Draw inspector | Percent complete vs budget line | $150–$350 per visit |
| Structural engineer (if flagged) | Foundation, framing | $500–$1,200 |
| MEP inspector (some lenders) | Rough-in before drywall | $300–$600 |

You cannot substitute your GC’s sign-off for the lender inspector — ordering drywall before rough-in inspection passes is the **#1 draw rejection** on investor builds. Schedule inspections **48 hours before** you need the wire; same-day requests rarely fund.

## Spec vs custom build — draw cadence differences

| Build type | Draw count | Lender comfort | Common delay |
| --- | --- | --- | --- |
| Spec (no buyer) | 8–12 | LTARV caps leverage | Market absorption at CO |
| Pre-sold custom | 6–10 | Higher LTC if contract in file | Buyer selection changes |
| Build-to-rent (BTR) | 10–14 | DSCR exit modeled | Lease-up after CO |

Spec builds often front-load **framing and dry-in draws** (40%–50% of budget by month 4) because lenders want the structure weathertight before releasing finish dollars. Custom builds with a signed contract may release finish draws faster — but change orders from the buyer still trigger re-inspection. Pair this guide with [construction-to-DSCR refinance](/blog/when-construction-to-dscr-refinance-makes-sense/) when your exit is hold, not sale.

## Draw package checklist — what the lender expects each time

Every draw request should include:

1.  Signed draw request form with line-item completion percentages
2.  Invoices matching budget categories (not lump-sum GC invoice)
3.  **Unconditional lien waivers** from GC and all subs paid on prior draw
4.  Dated photos of completed work (geo-tagged preferred)
5.  Updated schedule showing next milestone date

Missing any item delays funding **5–10 business days** — you pay IO on the full commitment while waiting. Submit packages through the channel your lender specifies; email attachments without a draw number often sit in queue behind complete files.

## Soft costs in draw schedules — permits, fees, and interest reserve

Ground-up budgets split **hard costs** (labor and materials) from **soft costs** (permits, architect, engineering, loan fees). Lenders release soft costs on different schedules:

| Soft cost | Typical draw timing | Documentation |
| --- | --- | --- |
| Building permit fees | Draw 1 or pre-close | Paid receipt |
| Architect progress billing | Draws 2–4 | Invoice + % complete |
| Interest reserve | Held by lender | Released monthly to pay IO |
| Contingency line | Last 5%–10% | Change order approval |

Interest reserve held in the loan commitment pays your **monthly IO** so you do not wire cash during build — verify whether your term sheet includes interest reserve or expects sponsor-funded IO from day one. Missing interest reserve on a 12-month build adds **$35K–$45K** in sponsor cash need beyond equity injection.

## Ground-up construction draws — tie schedule to exit

Draw schedules are the operating rhythm of any ground-up investor build — spec, custom, or build-to-rent. Model retainage, weather delay, and inspector lead time before you sign a 12-month term sheet at **8.99%–13.5%** IO. Your exit determines how tight the schedule must be: spec-to-sell needs CO aligned with absorption season; build-to-rent needs lease signed before the last retainage release so [construction-to-DSCR](/construction-to-dscr-rental-takeout-financing/) can pay off the construction balance. [New construction loans for investors](/new-construction-loans-for-investors/) covers program leverage; this guide covers the monthly mechanics that keep draws funding on time.

[**Pre-qualify for construction financing**](/scenario/)

## Related financing resources

Explore Jaken Finance Group programs and trusted reference material connected to this topic.

### On this site

-   [Get Construction Terms](/newbuild/)
-   [Construction financing for investors](/new-construction-loans-for-investors/)
-   [Construction cost and value calculator](/luxury-spec-ltc-calculator/)
-   [Ground up construction loans no experience](/ground-up-construction-loans-no-experience/)

About the author

Jason Taken is the Principal of Jaken Finance Group, a licensed Illinois attorney, and a licensed Realtor. He underwrites investor deals nationwide and writes the market analysis published on this site. [More about Jaken Finance Group](/about/)

## Review financing for your build

Share the site, construction budget, plans, and exit strategy to request construction financing terms.

[Get Construction Terms](/newbuild/) [Contact Us](/contact-jaken-finance-group-by-email/)

Or call [(833) 264-7776](tel:8332647776)