# Construction loan draws, interest and delay costs.

See when loan dollars reach the project, how a funded balance creates interest, and what a slower schedule could cost.

[Use the calculator](#workbench) [Read the guide](#guide-content)9 minute guide · Interactive tool

At a glance

The estimator calculates monthly interest on opening principal plus half of that month’s advance, using the entered annual rate divided by twelve. Interest is paid separately in this model. Added delay months hold ending principal constant and add interest plus entered other carrying costs; they do not create extension rights.

In this guide

Put it into practice

## Draw & delay estimator

Hypothetical starting values. Edit the assumptions, calculate, then explore a different case.

Your scenario

### Results, explained.

Inputs are processed in your browser. These results are educational estimates, not an eligibility or financing decision.

## Separate commitment, advances and available cash

A commitment is the total facility contemplated by the agreement. An advance is money funded under that agreement. The two amounts need not be the same on closing day. If a hypothetical $1.8 million commitment begins with a $300,000 advance, $1.5 million remains undrawn before any later activity. That remaining amount is not automatically available to spend immediately.

Ask what must happen before each advance, who submits the request, and how long review and payment could take. Maintain a project calendar with invoice dates, draw submissions, inspections and expected disbursements. A contractor’s payment deadline and the lender’s draw review are separate events.

## Make the draw request easy to reconcile

A useful request connects each claimed expense to a budget line and an evidence item. Keep the original budget, approved changes, previously funded amounts, current request and remaining cost to finish visible together. The [NCUA construction guide](https://publishedguides.ncua.gov/examiner/Content/ExaminersGuide/Commercial%26MBL/CandD_Loans.htm) describes draw reconciliation, inspection and final-funding controls for credit unions. Your transaction’s documents determine the actual requirements.

An inspection can support the funding review, but it does not replace your own accounting or guarantee construction quality. Ask how stored materials, deposits, disputed invoices and retainage will be handled. Retainage is an amount held back under the applicable arrangement; use the negotiated amount rather than assuming a universal percentage.

## Estimate interest on a visible schedule

The estimator uses a simple monthly convention: **opening principal plus half of that month’s advance**, multiplied by the annual rate divided by twelve. It assumes each advance occurs halfway through the month. For a $300,000 opening balance, a $100,000 advance and a 10% annual rate, estimated interest is **$2,916.67** for that month.

The following month opens at $400,000 because this model treats interest as paid separately. It does not add interest to principal. Enter each month’s advance directly, including zero for a month without funding. The tool checks that total principal advances do not exceed the entered commitment. Its chart shows the modeled funded balance over time.

Actual loan calculations can use specific funding dates, day-count conventions, changing rates, additional fees and financed interest. If interest is advanced from the loan, those advances can consume commitment and affect future interest. This simplified model does not solve that circular calculation. Its separate reserve input is only an amount available to cover modeled interest, not extra funding added to the loan.

## Give delays a dollar amount

The delay scenario holds the completed base schedule’s ending principal constant for the added months, with no new draws or principal repayments. At $1.5 million and 10% annual interest, three added months create **$37,500** of extra interest. If other carrying costs are $2,500 per month, the combined incremental burden is **$45,000**.

Those are arithmetic assumptions, not an extension quote. The scenario excludes extension fees and does not establish a right to extend. Compare the delayed payoff date with the actual maturity date, then ask what happens if they no longer align.

## Reconcile the interest allowance

The [OCC commercial real estate handbook](https://www.occ.treas.gov/publications-and-resources/publications/comptrollers-handbook/files/commercial-real-estate-lending/pub-ch-commercial-real-estate.pdf) explains that reserves must be evaluated against disbursement timing, interest rates and completion or lease-up assumptions. Use the tool’s base and delayed results to revisit your allowance. If modeled interest exceeds the entered reserve, identify the cash shortfall explicitly. A remaining reserve balance is not evidence that the overall construction budget is adequate.

## Read the monthly schedule one column at a time

Opening principal is the debt outstanding before that month’s construction advance. The advance increases principal. Ending principal becomes the next month’s opening principal because this model does not include repayments or add interest to the balance. Interest is shown as a separate cost, with cumulative interest available in the CSV export.

In the starting schedule, the first month opens at $300,000 and adds a $100,000 advance. Ending principal becomes $400,000. The interest basis for that month is $350,000 under the midmonth convention. At the entered hypothetical 10% annual rate, the estimated monthly interest is $2,916.67. A different actual advance date or contractual convention can produce a different charge.

| Schedule item | What it represents | What it does not establish |
| --- | --- | --- |
| Commitment | Entered principal funding limit | Cash already disbursed or unconditional access to funds |
| Monthly advance | Principal assumed to reach the project that month | The contractor’s invoice date or draw approval date |
| Ending principal | Initial funding plus advances to that point | A payoff statement including every fee and charge |
| Interest allowance | A separate amount compared with modeled interest | Additional principal or a promise that interest will be funded |
| Delay cost | Added interest and entered other carrying costs | An extension agreement or an extension-fee quote |

## Worked comparison: early and late advances

To isolate timing, consider a hypothetical two-month illustration with a $300,000 initial balance and $1.2 million of additional principal. This is an arithmetic demonstration, not a proposed loan term. Both schedules finish with $1.5 million outstanding, but they create different interest costs at the same entered 10% annual rate.

If the entire $1.2 million advance occurs in month one under the midmonth convention, first-month interest is $7,500. Second-month interest on $1.5 million is $12,500. Total modeled interest is $20,000. If the same advance occurs in month two, first-month interest is $2,500 and second-month interest is $7,500. Total interest is $10,000.

The $10,000 difference comes entirely from the assumed funding dates. It does not mean an advance can be postponed without consequences. Contractor payments, deposits and material purchases may still require cash. Compare the interest saving with the project’s actual spending calendar before choosing a draw assumption.

## Build the advance schedule from the work plan

Begin with the contractor’s expected work and payment milestones. Then distinguish when an invoice is expected, when a draw request can be submitted and when funding might arrive. These dates may differ. Enter anticipated principal advances in the estimator, and maintain the invoice and reimbursement calendar separately.

A practical draw log identifies the budget line, invoice reference, requested amount, previously funded amount, review status and expected receipt date. Keep approved changes linked to the updated cost-to-finish estimate. If a request has been reduced or delayed, revise the cash plan rather than leaving the earlier expected receipt in place.

Treat inspections, documents for payments and any holdbacks as transaction-specific matters. Ask what evidence supports each release and who is responsible for obtaining it. An estimated advance in this tool is not a confirmation that a draw will be approved. Your own project records should remain useful even when the lender’s reporting format differs.

## Stress timing without changing every assumption

Start by moving a planned advance to another month while preserving total principal. Observe the interest change. Next, restore the base schedule and add delay months. Then change other carrying costs separately. Testing one change at a time makes the cause of the result visible and helps avoid blaming a cost increase on the wrong assumption.

The published delay example holds principal at $1.5 million for three extra months. At the hypothetical 10% annual rate, added interest is $37,500. Entering $2,500 of other monthly carrying costs adds $7,500, for a combined delay burden of $45,000. The allowance comparison uses interest alone, so the other carrying costs still need a funding source.

For the starting case, total interest of $127,500 exceeds the entered $120,000 allowance by $7,500. That shortfall is separate from the $7,500 of other delay carrying costs. Combining those obligations requires $15,000 beyond the interest allowance for this modeled delayed case, assuming the allowance is available as entered. Keep the categories distinct when updating the [project budget](/ground-up-construction/budgets-equity/).

## Understand the commitment warning

The estimator checks the initial advance and subsequent principal advances against the entered commitment. If a month would exceed that limit, it clears the results and identifies the problem. Reducing a draw solely to remove the warning may leave the construction spending plan unfunded. Reconcile the missing dollars with equity, a revised scope or another separately reviewed source.

A commitment above the scheduled ending principal is not automatically a surplus available to the borrower. The model does not evaluate restrictions, reserves or whether additional advances meet the agreement. It also does not model principal repayments followed by redraws. Use an actual lender-approved funding schedule for those features.

## Use the result before discussing maturity

Put the expected completion date, the end of leasing or sales, and contractual maturity on the same calendar. A three-month delay in construction might also change the date at which an exit is possible. The delay estimator holds ending principal constant; it does not rebuild a lease-up or unit-sales timetable. Revisit [rental refinance or condo-sales proceeds](/ground-up-construction/planning-exit/) when that timetable changes.

Export the schedule with its assumptions and keep the original base case. Ask how interest is actually calculated, how any reserve is controlled, and what options exist if the project outlasts maturity. An educational delay result cannot establish those contractual rights. Add unanswered questions to the [readiness checklist](/ground-up-construction/readiness/) before relying on the schedule.

## Frequently asked questions

### How does the construction draw calculator estimate interest?

For each month, it multiplies opening principal plus half the monthly advance by the entered annual rate divided by twelve. This assumes midmonth funding. Actual funding dates, day-count conventions, fees and contractual terms may produce different charges.

### Does the interest allowance increase loan principal?

No. The allowance is compared with modeled interest and is not added to principal. This tool assumes separately paid interest. If interest is funded from the loan, obtain a transaction-specific advance schedule because those advances can affect commitment use and future interest.

### What happens when scheduled advances exceed the commitment?

The calculator clears the results and identifies the month that would exceed the entered commitment. Reconcile the excess with the actual spending and funding plan. Reducing an advance only to remove a warning can leave project expenses unfunded.

**Keep assumptions visible.**

Confirm project terms and support the figures you use before relying on a scenario.

[Prepare your project →](/ground-up-construction/readiness/)

Keep building your plan

## Construction Loan Exit Calculator: Refinance or Sales

A finished building is a milestone. A credible repayment plan connects that milestone to the cash needed to retire construction debt.

[Continue to the next guide](/ground-up-construction/planning-exit/) [← Previous: Budgets & equity](/ground-up-construction/budgets-equity/)

Updated November 2, 2026 · Published by Jaken Finance Group. General references are linked beside the relevant discussion; bank and credit-union guidance does not establish this product’s terms. Product parameters are from the supplied brief and have not been independently confirmed as a current offer.