# Phase 1 Construction Financing for Commercial Projects

See when Phase 1 can qualify for its own commercial construction loan. Budget shared roads and utilities, test standalone cash flow and plan future releases.

[Request Commercial Financing](/commercial-loan-request/) [Contact Us](/contact-jaken-finance-group-by-email/)

Updated November 2026

You may be able to **finance Phase 1 on its own** if it can finish, open, operate and repay its loan when Phase 2 is delayed. If the first building needs $1.8M of roads and utilities to open, show who pays that full $1.8M and when the bills come due.

## Phase 1 funding and payoff calculator

Test the cash needed to build the first phase and whether its own refinance can cover the payoff.

### Estimated results

Total Phase 1 budget

$11,200,000

Cash needed for Phase 1

$2,400,000

Shared costs fronted beyond allocation

$900,000

Refinance surplus or shortfall

$100,000

Deal summary How the estimate adds up

-   The cash case uses the full shared cost due in Phase 1. The exit uses only Phase 1 proceeds. A negative refinance result means more money is needed to pay off the first loan.

Borrowers

[Submit a Phase 1 construction deal](/commercial-loan-request/?typeOf=Phase+1+standalone+construction+financing)

Brokers with a client deal

[Sign up as a broker](https://brokers.jakenfinancegroup.com)

[Check whether Phase 1 can open](#what-does-phase-1-need-to-open) · [Run the 48-unit example](#worked-example-with-48-apartments-in-phase-1) · [Prepare the lender request](#what-should-you-send-for-a-phase-1-loan-review)

## What does Phase 1 need to open?

Draw a line around Phase 1 on the full site plan. Then mark everything the people using it will need on opening day. Include work outside the line if the first building relies on it. A road can be on the next parcel and still be required for the first building to open. A sewer connection can serve both buildings and still have to be paid for up front.

| Phase 1 dependency | What to show the lender |
| --- | --- |
| Roads and access | The route for residents, deliveries and emergency vehicles, plus who will build it and when |
| Water, sewer, power and drainage | Which lines and systems need to be in service, approvals from the parties providing them and a bid for the work |
| Parking, paths and common space | Which parts must open with Phase 1, including accessible routes, and which can wait for Phase 2 |
| Permit and occupancy milestones | Which permits apply to each scope, who issues them and what inspections or work are needed to open Phase 1 |
| Protection from active construction | How the first building will stay accessible and safe while the next phase is being built |

Ask the local building and planning authorities what they need to approve occupancy for the first building. Bring a site plan with the proposed limits of work and a timeline for shared improvements. For example, Pierce County’s process for temporary occupancy calls for site safety and emergency access even when work is still underway. Confirm the requirements for your own site and whether the lender will accept a temporary certificate. [Pierce County’s temporary occupancy procedure](https://www.piercecountywa.gov/DocumentCenter/View/130945/PPW-Procedure---Temporary-Certificate-of-Occupancy?bidId=)

A lender also wants to know how long that setup can work. If Phase 1 can open with temporary parking or a temporary access road, ask how long approvals and easements would last. Price repairs, lighting, security and other costs during that period. Ask who pays if later work runs through the temporary route. Draw the route the property manager will use while both phases are active.

### Who runs the common facilities once Phase 1 opens?

Give the property manager a list of the systems the first building will use. Who clears the road, pays the power bill for site lights and maintains the drainage system? Put those costs in the Phase 1 operating budget through the date a second owner can reliably start paying a share. If Phase 2 never starts, show who will handle the work and how Phase 1 will pay for it.

Check how meters, service agreements and access are set up. If all the lights are on one account, for instance, who sees the bill and how does the other owner pay its share? Have counsel document the terms and discuss how they would carry over to a buyer. Give the lender the actual agreement so it can decide which payments to recognize when sizing a refinance.

## Which loan structures can work for a phased build?

Ask whether the lender is financing Phase 1 by itself or offering one loan for the site with funds released in stages. Both can fit a phased job. Each gives you a different set of rights and conditions when the next phase is ready.

| Financing structure | What to confirm up front |
| --- | --- |
| A construction loan for Phase 1 | Which parcels secure it, whether Phase 1 has its own budget and exit, and how later land can be released |
| One construction facility with staged advances | How much is committed for each stage, what releases funds for the next stage and how maturity dates work |
| Separate financing for land and infrastructure | Which loan pays each common bill, how the land lender is repaid and when building work can be funded |

Give each proposed lender the same site plan and budget. Ask which roads or utilities the loan can advance against and what needs to be in place before work on the building starts. If one lender funds the infrastructure, ask what the building lender needs to see before it funds the first building. Bring both timelines to the discussion. The OCC handbook describes how banks monitor work, advances and whether funding is sufficient to finish. [OCC commercial real estate lending handbook](https://www.occ.gov/publications-and-resources/publications/comptrollers-handbook/files/commercial-real-estate-lending/index-commercial-real-estate-lending.html)

If a single loan covers the whole site, find out which advances are committed and which require a new credit decision. Ask what can make later funds unavailable. The lender might want more leases, a new appraisal or extra cash before it releases money for the next building. Have the lender lay out when each stage starts and what happens to the loan if you decide to stop after Phase 1.

## Worked example with 48 apartments in Phase 1

A developer plans **96 apartments in two 48-unit phases**. The site plan puts the permanent access road, main utility connections and drainage work in the first phase. Those improvements will also serve the second building. Assume the first 48 apartments need that shared work to get occupancy approval and the bills come due during Phase 1.

| Phase 1 costs | Amount due or contributed |
| --- | --- |
| Phase 1 land value the lender agrees to credit | **$1.2M** |
| First building, soft costs, carry and contingency | **$8.2M** |
| Shared access road | **$600K** |
| Shared water and sewer connections | **$700K** |
| Shared drainage and electrical work | **$500K** |
| Total Phase 1 budget including the land contribution | **$11.2M** |

The developer’s full-site budget assigns half of the **$1.8M** common work to each phase. Using that split to plan the first loan would show a $10.3M Phase 1 budget. Assume a **$7.6M construction commitment** and **$1.2M** of land equity, with the Phase 1 land free and clear. On that split budget the developer would plan for $1.5M of cash. With all the shared bills due in Phase 1, it needs **$2.4M in cash** at that same loan amount. The extra **$900K** has to be funded even if the developer plans to recover part of it later.

Use a site-wide budget to track which phase ultimately bears each cost. Use a draw schedule to show who pays when a bill comes due. If Phase 2 will reimburse a share, show the agreement and when the money would be available. Give any assumed funding from the second phase its own line. Underwrite a case with no payment from Phase 2. If that case comes up short, get a firm source of cash for the first building or revise the work and confirm it can still open.

### How much cash has to be available before draws?

In the same example, suppose **$1.1M** of the shared work comes due before the first lender reimbursement for those bills. The sponsor has **$850K** in cash free that week after other costs. It has a **$250K timing gap**. Those infrastructure bills were already in the $11.2M budget. The extra cash has to be available earlier than the original schedule shows.

Ask how much the lender will fund at closing, when it makes the first draw and what evidence it needs to pay for work in progress. Have the contractor mark long-lead orders, deposits and utility fees in the payment schedule. Check who can pay if an inspection happens later than planned. Use the [construction draw and interest calculator](/ground-up-construction/draws-interest/) to test the dates and interest on your own loan.

## Can Phase 1 refinance while Phase 2 waits?

Build the exit from the first building’s rent and expenses. Include what Phase 1 pays to run and maintain common areas. Ask how the appraiser or lender will treat payments expected from other phases. There can be a difference between Phase 1’s actual cash cost while it is on its own and the share it might pay once the site is fully built.

For the 48-unit example, assume Phase 1 earns **$750K in stabilized annual net operating income**. That is the rent and other operating income left after property operating expenses, before debt service. Use a hypothetical refinance with a **6.25% capitalization rate**, a **65% loan-to-value cap**, and a **1.25× debt-service coverage test**. Assume $75,000 of annual debt service per $1M of new loan. That payment factor lets you translate what rents can support into a loan amount.

| Refinance test using only Phase 1 | Result |
| --- | --- |
| Value and loan at $750K of annual net operating income | $750K ÷ 6.25% = **$12M value**. At 65%, the loan ceiling is **$7.8M**. |
| Loan supported by debt service at that income | $750K ÷ 1.25 supports $600K of annual debt service, or **$8M** of loan proceeds. |
| Base proceeds against the construction payoff | The lower limit is $7.8M. After $100K in fees and an assumed $7.6M payoff, there is **$100K left**. |
| Value and loan with lower net operating income of $690K | $690K ÷ 6.25% = $11.04M of value. At 65%, the ceiling drops to **$7.176M**. |
| Debt-service test and net proceeds in the lower income case | Coverage permits $7.36M, so value still controls. After $100K in fees, $7.076M leaves a **$524K payoff gap**. |

The lower income case assumes Phase 1 has **$60K more in annual common costs** and the refinance lender underwrites those costs as ongoing. Use a different test for a temporary expense with a firm end date. If Phase 2 starts a year late and Phase 1 pays that $60K for only one year, budget the actual cash and ask how the refinance lender will treat it. Check how soon the first building can be ready, leased and collecting rent. A longer lease-up can add to the funding need even if full occupancy eventually supports the modeled loan. [Construction exit calculator](/ground-up-construction/planning-exit/) · [Apartment lease-up refinance guide](/apartment-lease-up-refinance/)

## Can you keep the next parcel available for its own loan?

Get a survey and a title review early. Show which parcels the first lender will take as security and which site rights connect them. If the first phase uses a driveway or utility line on future land, confirm how it will keep using those facilities after a sale, refinance or change of ownership. Ask the title team and counsel what rights need to be recorded and who has to agree.

Ask the first lender what it would take to release the next parcel. Will it permit a release before the first building opens or after a specific milestone? Will you have to make a principal payment or provide another report? Ask when the lender values the remaining collateral and who pays the cost of the release. Put the expected release date and amount in your Phase 2 budget. If the second lender must fund the release, make sure both sides can close in the same order.

For example, take a separate scenario where the first lender asks for a **$500K paydown** to free the next parcel. If the Phase 2 lender can put **$300K** toward the release at closing, the sponsor must still supply **$200K**. Give the closing team both lenders’ conditions. One lender may want the parcel released before its lien can attach while the first wants payment before signing the release. Confirm whether they can close together and what needs to be held in escrow. If the release can happen, reflect the paydown in the first loan’s future payoff and in the second phase’s sources and uses.

Also ask whether a default on one phase can trigger a default under the other loan. That can matter even when the project has two entities and two budgets. Explain how you plan to pay for shared services and how a lender can enforce its rights if the two phases have different owners later. Document the planned boundaries and rights while you can still change them.

## What should you send for a Phase 1 loan review?

Lead with the property address, full development plan, what Phase 1 will deliver, the requested loan and the next deadline. Tell the lender which costs, approvals and rights affect whether Phase 1 can open on schedule. Show the Phase 1 exit with later construction delayed.

-   **Site and phase map.** Mark the work limits, parcels, access and common facilities. Show where construction equipment and residents will move while the next phase is underway.
-   **Permits and utilities.** List approvals in hand, what is outstanding and who is responsible for each date. Identify any condition that affects first occupancy.
-   **The first budget and draw schedule.** Break out the costs unique to Phase 1 and the shared work. Match each bill with its funding source and due date.
-   **Collateral and future releases.** Share the survey or parcel map, ownership, proposed collateral and any current debt. Identify which parcel you expect to free up and when.
-   **Standalone exit.** Include a rent and expense forecast, the expected construction payoff and how the project would cover any refinance shortfall.

When you know the first scope and loan amount, [request commercial construction financing](/commercial-loan-request/). If the request is for roads, utilities or finished lots before the buildings, review [acquisition and development financing](/acquisition-and-development-loans/). If you still need to close on the land, start by testing [the cost of buying the site before building permits](/land-acquisition-before-construction-permits/).

## Related financing resources

Explore Jaken Finance Group programs and trusted reference material connected to this topic.

### On this site

-   [Commercial real estate financing](/commercial-real-estate-financing/)
-   [Multifamily DSCR vs commercial loan (no unit maximum)](/blog/multifamily-dscr-vs-commercial-loan/)
-   [Mixed-use vs multifamily financing](/blog/mixed-use-vs-multifamily-financing/)
-   [Commercial bridge loan vs SBA loan](/blog/commercial-bridge-loan-vs-sba-loan/)

## Frequently asked questions

Can I get a construction loan for Phase 1 on its own?

Some lenders will finance the first phase if it has enough funding to finish, can open and earn income on its own, and has a viable way to repay the loan. Show which shared improvements must be in place before anyone can occupy the building.

Can a Phase 1 loan fund roads and utilities used by later phases?

It may fund approved common work. Show the full cost, which bills come due in Phase 1 and who will fund them. If the first lender covers only part, identify a committed source for the rest.

Does Phase 1 need a separate parcel to get construction financing?

Ask the lender and title team what collateral they will accept. If the loan covers future parcels, confirm how those parcels can be released and which recorded rights Phase 1 needs for access, utilities and use of shared space.

What happens if Phase 2 is delayed or canceled?

Rework Phase 1's budget and refinance using only its own rents, operating costs and available funds. Check whether it can still finish, open, pay for common facilities and repay its loan. Ask how the construction terms treat a delay in later work.

What should I give a lender for a Phase 1 construction loan?

Share the full site plan and the Phase 1 limits, required approvals, shared infrastructure bids, a draw schedule, the collateral proposal and exit math. Identify any parcel release, utility approval or funding source that still needs to be confirmed.

## Ready to fund your next deal?

Get pre-qualified in minutes. Speak with a lending specialist or submit your scenario online.

[Request Commercial Financing](/commercial-loan-request/) [Contact Us](/contact-jaken-finance-group-by-email/)

Or call [(833) 264-7776](tel:8332647776)