# Spec Home Construction Loans for Investors

Spec home construction loans for investors — 8.99%–13.5% interest-only, inspected draws, 12–18 months. Sell or refinance after CO. Jaken Finance Group.

[Pre-Qualify Today](/scenario/) [Contact Us](/contact-jaken-finance-group-by-email/)

Updated September 2026 Rates as of August 2026

You control a legal lot. Plans exist or are in permit. There is **no signed buyer**. That is a **spec home construction loan** — not a custom-home mortgage, not a flip, and not a subdivision facility.

Jaken Finance Group funds qualified investor spec builds nationwide at **8.99%–13.5%** interest-only on the drawn balance. Term is **12–18 months** (extensions available). The loan always funds the **lower** of loan-to-cost and **75%** of as-completed value. Close targets **10–14 business days** when plans, budget, and title are already in the file. After certificate of occupancy you sell, or you refinance to [DSCR](/dscr-loans/) at **5.75%–10.5%**.

Apply: [new construction application](/newbuild/). Still choosing among land, a plat, or a stalled vertical? Start at [new construction loans for investors](/new-construction-loans-for-investors/).

[CFPB consumer-mortgage rules](https://www.consumerfinance.gov/ask-cfpb/what-is-a-mortgage-in-general-en-112/) apply to dwellings the borrower occupies. This product is **business-purpose** and **non-owner-occupied only**. Do not apply if you plan to live in the house. **This is educational information, not legal or tax advice.**

## What “spec” actually means

**Spec** means you are building for the market. The house is not under contract. You pick the plans, carry interest and taxes through construction, and take the sale or rental risk at the end.

The [Census Bureau’s New Residential Construction series](https://www.census.gov/construction/nrc/index.html) tracks housing starts and completions nationally. Those tables tell you the country is still building. They do not tell you whether _your_ lot, _your_ comps, and _your_ permit clock will finish inside a 12–18 month interest-only term. That is the underwriting question.

| You have | Product that fits | Product that does not |
| --- | --- | --- |
| One entitled lot, house plans, sell or rent at CO | Spec construction loan | Land or subdivision |
| A contracted buyer who already chose finishes | Custom / construction-to-perm elsewhere | Spec |
| A standing house that needs rehab | [Fix and flip](/what-is-a-hard-money-loan/) | Spec |
| Acreage with no recorded lots | [Vacant land](/vacant-land-loans-raw-land-financing-investors/) | Spec |
| Streets and utilities still to build | [Subdivision financing](/subdivision-development-financing/) | Spec |
| A purpose-built rental pod, not one MLS sale | [Spec / BTR for builders](/spec-home-build-to-rent-financing-for-builders/) | One-lot spec |
| $900K-plus finished value, thin buyer pool | [Luxury new construction](/luxury-new-construction-loans/) | Standard spec |
| First vertical, thin builder resume | [Ground-up with no experience](/ground-up-construction-loans-no-experience/) | Repeat-builder spec |

For a spec home, the sale of the finished house must repay the loan. Link the lot basis and planned finishes to comparable completed sales. If subdivision or utility work is still required, show it as a separate phase rather than assuming that the entire budget is ready to fund.

A **presale** (a buyer under contract before CO) reduces carry risk. It is not required on qualified investor files. If you have one, bring the contract. If you do not, bring comps and a days-on-market plan that survives a slow season.

## National terms — then the two caps

Draw-by-draw mechanics live on [how construction loans work](/blog/guide-construction-loans/) and the [new construction investment property guide](/blog/new-construction-investment-property-guide/). The settings that size a Jaken Finance Group spec file:

| Parameter | Setting | National note |
| --- | --- | --- |
| Rate | **8.99%–13.5%** interest-only on the **drawn** balance | Priced to sponsor and file |
| Term | **12–18 months** IO; extensions available | BTR verticals can run 12–24 months — that is a different product |
| LTC — qualified files | Up to **100% LTC** on qualified files | Still cannot beat the value cap |
| LTC — general investor | Up to **90% LTC** | Most one-lot investor specs |
| LTC — repeat spec / BTR builder | **70%–80% LTC** | Track record and sell-out history |
| LTC — first vertical | **65%–75%** of cost | Pair with [no-experience ground-up](/ground-up-construction-loans-no-experience/) |
| As-completed cap | Up to **75% LTARV** | We fund the **lower** of LTC and LTARV |
| Contingency | **10%–15%** of hard-cost budget | Winter, coastal insurance, and long permits argue for the high end |
| Interest reserve | **2–4 months** typical; **~6 months** first-time or winter/long-permit | Charged on draws, not the unused commitment |
| Draws | **5–7** on a $500K-plus vertical | Never more than **20%** before foundation inspection |
| Draw funding | **48–72 hours** after third-party inspection | Change orders need paper before the next draw rises |
| Close | **10–14 business days** | Clock starts when appraisal payment and conditions are in |
| DSCR takeout | **5.75%–10.5%**, typically **70%–75% LTV** | Just-completed specs are not seasoned rentals |

Two rules carry most of the file. First, we **fund the lower of LTC and LTARV**. A cheap lot with a fat vertical usually binds on cost. An expensive lot with a modest house usually binds on the **75%** value cap. Second, we **do not front-load more than 20% of the budget before the foundation inspection**. Dirt and hopes are not a house.

## How the two caps actually bind

**Loan-to-cost** is a share of land basis plus vertical budget. Vertical means hard cost, soft cost, and a **10%–15%** contingency on the hard-cost line — not a vibe.

**Loan-to-as-completed value** is **75%** of supported finished value from comps of the same product, finish, and school or location tier.

“Up to **100% LTC** on qualified files” is real. It still loses to **75%** of value when that number is lower.

### Worked file A — production infill, cost and value almost tie

Illustrative. Your bids and comps replace these numbers.

| Line | Amount |
| --- | --- |
| Lot basis | $95,000 |
| Hard cost | $250,000 |
| Soft cost (plans, permits, utilities, insurance) | $30,000 |
| Contingency 12% of hard cost | $30,000 |
| **Total cost** | **$405,000** |
| As-completed comps | $485,000 |
| **75% LTARV** | **$363,750** |
| **90% LTC** | **$364,500** |
| **Loan (lower of the two)** | **$363,750** |
| **Cash to close** | **$41,250** plus reserves |

A first-time sponsor on the **same dirt** at **70% of cost** sees a **$283,500** loan and about **$121,500** cash. The lot did not change. The resume and liquidity did.

### Worked file B — land-heavy lot, value cap wins by a wide margin

| Line | Amount |
| --- | --- |
| Lot basis | $280,000 |
| Hard cost | $180,000 |
| Soft cost | $22,000 |
| Contingency 12% of hard cost | $21,600 |
| **Total cost** | **$503,600** |
| As-completed comps | $580,000 |
| **75% LTARV** | **$435,000** |
| **90% LTC** | **$453,240** |
| **Loan (lower of the two)** | **$435,000** |
| **Cash to close** | **~$68,600** plus reserves |

The lot is more than half of cost. **90% of cost** is not available because **75% of finished value** is lower. That is the teardown pattern in high-basis neighborhoods — the same logic the [Illinois spec guide](/spec-home-construction-loans-illinois/) and [Texas spec guide](/spec-home-construction-loans-texas/) apply to local land, without copying their fee tables.

## Interest carry — what the coupon actually costs

Interest is charged on the **drawn** balance. A $363,750 commitment is not $363,750 outstanding on day one.

Illustrative at **11%** interest-only (inside the **8.99%–13.5%** band) on File A:

| Month | Approximate outstanding | Monthly IO at 11% |
| --- | --- | --- |
| 1–2 (site / foundation) | ~$70,000 | ~$640 |
| 3–6 (frame / dry-in / MEP) | ~$200,000 | ~$1,830 |
| 7–10 (finish / CO) | ~$340,000 | ~$3,120 |
| 11–12 (list / punch) | ~$363,750 | ~$3,330 |

Twelve-month carry on that curve is roughly **$22,000–$26,000**, not $40,000. If permitting slips 90 days before the foundation draw, you still owe taxes, insurance, and idle lot carry — and the interest reserve you booked at 2 months is gone. That is why first-time and winter-climate files should model closer to **6 months** of reserve, and why northern Q4 starts belong on a longer clock. See the [Illinois spec](/spec-home-construction-loans-illinois/) winter note and the [Colorado spec](/spec-home-construction-loans-colorado/) tap-and-weather notes when those jurisdictions are the risk.

Add property tax and builder’s risk for the full hold. A January 1 assessment that picks up the finished house — common in Texas appraisal districts — can double the tax bill in year two. Model the **post-CO** bill, not the vacant-lot bill. The [Texas spec construction](/spec-home-construction-loans-texas/) guide walks that calendar.

## Draw sequence and the 20% rule

Plan **5–7 draws** on a $500K-plus vertical. Typical gates:

| Draw | Gate | What the inspector is looking at |
| --- | --- | --- |
| 1 | Site / foundation | Footings, slab or basement, utilities in |
| 2 | Framing / dry-in | Structure, roof, windows, dried in |
| 3 | MEP rough | Mechanical, electrical, plumbing rough-in |
| 4 | Drywall / exterior | Insulation, drywall, siding or masonry |
| 5–6 | Finish | Interior finish, remaining exterior |
| Final | CO | Certificate of occupancy, punch, remaining retainage |

We **never advance more than 20% of the budget before the foundation inspection**. A large “mobilization” draw that funds the whole lumber package before there is a foundation is how files stall with a hole in the ground and no house.

Draws fund **48–72 hours** after a passing third-party inspection. Change orders need paper **before** the next draw amount goes up. Scope templates: [how to submit a scope of work](/guides/how-to-submit-a-scope-of-work/) and the [draw process](/guides/fix-and-flip-draw-process/).

If the original lender already stopped funding a half-built house, that is [mid-construction refinance](/mid-construction-refinance/) — remaining-work draws, not a new spec start.

## Timeline from contract to CO

A clean, entitled lot in a fast suburb can look like this. A city teardown will not.

| Phase | What has to be true | Why files slip |
| --- | --- | --- |
| Lot control | Deed, option, or purchase contract | You cannot size a loan on a lot you do not control |
| Plans | What the city will permit | Pinterest boards are not a plan set |
| GC | Licensed, insured, contracted | “GC TBD” is a stop |
| Appraisal / as-completed | Same-product comps | Wrong house type kills value |
| Close | Title, entity, insurance, reserve | Missing builder’s risk delays funding |
| Demo (if teardown) | Separate permit, utility disconnects | Dead carry between wrecking and vertical |
| Vertical | Inspection calendar | Weather, failed inspections, sub no-shows |
| CO | Punch and municipal sign-off | Punch lists eat the last 30 days |
| Exit | List or lease | Modeling zero days of post-CO carry is fiction |

Budget **60 days** of carry after the last draw on a retail sale. Luxury finish and thin buyer pools need more — see the [luxury spec exit playbook](/blog/luxury-spec-home-exit-playbook-60-120-days-on-market/).

Teardown sequencing is its own loan problem. You often close the lot, pull a wrecking permit, sit through utility disconnects, then convert or reopen into vertical. If you need to buy the house-plus-lot before demo, that first close can be a [bridge](/bridge-loans-for-real-estate-investors/) or land-plus-demo advance, then construction. Do not pretend the wrecking permit is the building permit.

## What underwriting actually reads

Bring the file, not a pitch deck.

1.  **Lot control** — deed, option, or purchase contract. Entitlement must match the plans.
2.  **Sealed plans** — what the city will permit.
3.  **Licensed GC contract** — hire first. We will check license class against project value where the city licenses by class.
4.  **Line-item budget** — hard, soft, and **10%–15%** contingency already on the hard-cost line.
5.  **As-completed comps** — same product, same finish and location tier. Do not import a different house type.
6.  **Exit** — list price and days-on-market plan, **or** rent, taxes, insurance, and a DSCR worksheet.
7.  **Entity and liquidity** — LLC docs, interest reserve, tax and insurance carry through CO.
8.  **Builder’s risk and GC insurance** — in force at close, lender named as required. State texture lives on guides such as the [Indiana builder’s risk guide](/your-indiana-builders-risk-guide/) and the [Florida hurricane builder’s risk guide](/hurricane-proof-your-flip-the-ultimate-florida-builders-risk-guide/).

We underwrite **this** build. Banks often want a stack of prior certificates of occupancy. Experience helps. A complete package on one house can still close. First verticals that still look thin should read [ground-up construction with no experience](/ground-up-construction-loans-no-experience/) before they apply.

## Two exits — run both before you pour

**Retail sale.** List after CO. Model commission, concessions, and **60 days** of post-draw carry. If the buyer pool is thin or the list is $900K-plus, you are on [luxury new construction](/luxury-new-construction-loans/), not a production spec.

**Hold as a rental.** Lease, then [DSCR](/dscr-loans/) at **5.75%–10.5%**. Just-completed specs take out at **70%–75% LTV**. Do not model **85%** permanent debt on a house that received a certificate of occupancy last week.

Illustrative DSCR takeout on File A at **72% LTV**:

| Line | Amount |
| --- | --- |
| Finished value | $485,000 |
| DSCR loan at 72% | $349,200 |
| Illustrative P&I at 7.25% 30-year | ~$2,380 |
| Taxes + insurance (illustrative) | ~$450 |
| **PITIA** | **~$2,830** |
| Rent that clears 1.0 DSCR | **~$2,830+** |

If market rent is $2,400, this house does **not** take out as a rental at that leverage. You sell, you add cash, or you do not start. Builder communities that were rental-by-design from day one belong on [spec / BTR financing](/spec-home-build-to-rent-financing-for-builders/) and [build-to-rent programs](/build-to-rent-financing-programs-for-developers-2026/).

## Bank construction vs this product

|  | Typical bank construction | Jaken Finance Group spec |
| --- | --- | --- |
| Occupancy | Often owner-occupied or presale | **Non-owner-occupied** investor only |
| Resume | Prior COs required | This file can carry a first vertical |
| Buyer contract | Often required | Optional |
| Advance | Cost-based, slow inspections | Lower of LTC and **75%** LTARV; 48–72 hour draws |
| Rate / term | Bank construction pricing, 9–12 months common | **8.99%–13.5%** IO, **12–18 months** |
| Close | Weeks to months | **10–14 business days** on a complete file |
| Exit | Sale to the contracted buyer | Sale **or** DSCR at **70%–75% LTV** |

Institutional overlays that decline “ground-up not supported” or “no builder resume” are a product redirect, not dead land. See [backup lender after institutional decline](/backup-lender-after-institutional-decline/).

## What kills spec files

-   **Owner-occupy intent.** We do not fund a house you will live in.
-   **Acreage with no plat.** Use [vacant land](/vacant-land-loans-raw-land-financing-investors/) or [subdivision](/subdivision-development-financing/) first.
-   **GC TBD.** There is no inspection counterparty.
-   **No contingency.** We will add **10%–15%** or pass.
-   **Wrong comps.** A ranch set does not support a two-story spec.
-   **Zero post-CO carry.** Lists do not fund the day the sticker goes up.
-   **85% DSCR takeout on a new CO.** Use **70%–75% LTV**.
-   **Four-to-twenty homes on one pad.** That is [community build construction](/community-build-construction-loans/).
-   **Backyard cottage or garage conversion.** That is [ADU construction](/adu-construction-loans/).
-   **Half-built, lender walked.** [Mid-construction refinance](/mid-construction-refinance/).

## Spec programs by market

National terms are the same. Permit clocks, taxes, insurance, and comps are not. Use the state guide when the jurisdiction is the risk:

-   [Illinois spec construction](/spec-home-construction-loans-illinois/) — Chicago teardown vs collar land-cash
-   [Indiana spec construction](/spec-home-construction-loans-indiana/)
-   [Florida spec construction](/spec-home-construction-loans-florida/)
-   [Georgia spec construction](/spec-home-construction-loans-georgia/)
-   [North Carolina spec construction](/spec-home-construction-loans-north-carolina/)
-   [Colorado spec construction](/spec-home-construction-loans-colorado/)
-   [Texas spec construction](/spec-home-construction-loans-texas/) — DFW and Austin MUD/PID and January 1 reassessment
-   [Washington DC spec construction](/spec-home-construction-loans-washington-dc/)

City construction pages for Chicago and DC add permit texture: [new construction loans Chicago](/new-construction-loans-chicago/) · [new construction loans Washington DC](/new-construction-loans-washington-dc/).

## Apply

[**New construction application**](/newbuild/) · [**Submit a scenario**](/submit-scenario/) · [**Pre-qualify**](/scenario/) · **(833) 264-7776**

_Rates, terms and conditions offered only to qualified borrowers and are subject to change at any time without notice. Closing times are in business days and commence upon receipt of appraisal payment and satisfaction of borrower conditions. All loans are subject to full underwriting for loan approvals. Jaken Finance Group only finances non-owner occupied investment properties._

## Related financing resources

Explore Jaken Finance Group programs and trusted reference material connected to this topic.

### On this site

-   [Ground up construction loans no experience](/ground-up-construction-loans-no-experience/)
-   [New construction loans for investors](/new-construction-loans-for-investors/)
-   [Multifamily construction loans (5–20 units)](/multifamily-construction-loans/)
-   [Small multifamily construction loans (5–9 units)](/small-multifamily-construction-loans/)

## Frequently asked questions

What is a spec home construction loan?

It is short-term, interest-only construction capital to build a house on an entitled lot without a signed buyer contract. Jaken Finance Group funds qualified investor files at 8.99%–13.5% on a 12–18 month term, with inspected draws and a 75% as-completed value cap. Exit is a retail sale or a DSCR refinance after certificate of occupancy.

How is a spec loan different from a custom-home or fix-and-flip loan?

A custom-home loan usually has a contracted buyer who already picked the plans. A flip starts with a standing house. A spec loan starts with dirt and plans, and you carry market risk until you sell or lease. That is why lenders want a real budget, a licensed GC, and a sell-or-rent exit written before the first draw.

What leverage and close speed apply to spec construction?

Jaken Finance Group funds the lower of loan-to-cost and 75% of as-completed value. Qualified files can reach up to 100% LTC. Repeat spec builders often land at 70%–80% LTC. First verticals typically sit at 65%–75% of cost. Complete packages target 10–14 business days to close.

Why does the 75% as-completed cap bind before cost leverage on some lots?

When land is a large share of finished value, 75% of as-completed value is often lower than 90% or even 100% of cost. We fund the lower number. That is why a seven-figure lot does not automatically produce a seven-figure construction advance.

How much interest reserve should I budget?

Plan 2–4 months of interest on a clean-climate, entitled lot. First-time sponsors and winter or long-permit markets should model closer to 6 months. Interest is charged on the drawn balance, not the full commitment, so a rising draw curve costs less than assuming the whole loan is outstanding on day one.

Can I convert a spec house to a rental if it does not sell?

Yes on qualified files after certificate of occupancy and a supportable rent. Permanent takeout is DSCR at 5.75%–10.5%, usually 70%–75% LTV on a just-completed spec — not the 85% purchase band used for seasoned rentals. Model both exits before you pour footings.

Where do I apply for a spec home construction loan?

Use the new construction application with sealed plans, a line-item budget, GC contract, lot control, and a written sale or rental exit. Submit a scenario if you are still choosing among spec, land, a small plat, or a stalled mid-build. Call (833) 264-7776 for a same-week sizing conversation on a complete package.

## Ready to fund your next deal?

Get pre-qualified in minutes. Speak with a lending specialist or submit your scenario online.