Buying a Development Site Before Building Permits

Compare a land loan, a construction facility and holding the site under contract. Price permit delays, the land payoff and the cash you need before closing.

Updated

You can buy a commercial development site before building permits are issued if you have a way to fund the purchase and carry the property. Compare a land loan, an approved land advance under a construction facility and keeping the site under contract while permits are pending.

Permit delay and land payoff calculator

See what a permit delay costs, when it runs past the land loan’s maturity and how much cash you still need at takeout.

Delay and available cash
Use cash available after acquisition and the original predevelopment budget.
Additional costs and payoff

Estimated results

Added cost of the delay
$166,400
Months past entered maturity
3
Cash still needed for delay and payoff
$108,400

How the estimate adds up
  • The model adds the entered extension fee if the delay runs past the stated maturity. Confirm that the extension is available. The closing advance can cover the land payoff when it is released.

Brokers with a client deal

Sign up as a broker

Compare your options · Price a six-month delay · Prepare your financing request

How can you control the site before permits?

Start with the seller’s deadline and your next approval. Ask whether you need to own the site now or can keep the right to buy it while plans are reviewed. Put those dates next to when each lender can close and what it can fund. A land loan or an initial construction advance can get you to purchase. You still need a plan for the months before work can start.

Way to control the siteWhat to confirm before you commit
Keep the property under contract or use an optionHow long you have, what you can do on the site, when deposits are at risk and what extensions cost
Buy with a land loan and arrange construction financing laterLand loan proceeds, the cash to close and carry, the loan maturity and how a construction loan would pay it off
Close an acquisition and construction facility in one transactionApproved land advance, conditions for later draws, when interest and maturity start and what happens if approvals slip

A purchase agreement can give you time to test the site and apply for approvals with the owner’s consent. Have the seller and your counsel confirm your rights to enter the property and commission surveys, soil work and other studies. Ask when you are allowed to submit plans. Write down which deposits are refundable, when that changes and who has the right to extend. If you pay for plans before closing, include those costs when comparing what it costs to wait with what it costs to own.

For a land loan, ask how the lender values the property in its current condition and how it sizes advances. If it can fund some design or site expenses, get the approved amounts and dates. The construction lender will make its own decision later. For a single facility, ask how much goes out at the land closing and what needs to happen before the next dollar can fund. Ask when the lender can change or cancel undrawn funds and what it would take to extend the commitment. OCC commercial real estate lending handbook

What should you check if one lender funds both stages?

Get a list of what unlocks the first building advance. It may include issued permits, a signed contract, the final budget or an equity deposit. Check what the lender can ask for again if the plans or costs change. With a land advance outstanding, the project needs cash to pay interest and other bills while those conditions are open.

Find out when the loan clock starts. For example, suppose a separate facility matures 18 months after buying the land. If the building can start in month twelve, only six months are left before maturity. A fourteen-month build will need more time even before leasing. Ask whether the term starts when you buy or when you begin construction, and get the actual dates and any extension terms. Build the lease-up or sale schedule into the same timeline.

Which approvals are still open?

“Permits pending” can describe several different risks. A site with the proposed use already allowed and plans in building review is at a different stage from one that still needs rezoning or a special approval. Ask what has been approved in writing, what conditions came with it and who can confirm the next step. Grand Rapids, for example, describes separate land-use and building permit plans for most commercial projects. Grand Rapids commercial zoning and permit process

What to checkWhat to collect
Permitted use and densityZoning and other land-use decisions for your actual building, with open conditions and hearing dates
Site and infrastructureSite plan status, access approvals, utility capacity and costs for any line, road or drainage work required
Plans and building permitsPlan submission date, open comments, remaining drawings, fees and any separate permits for early work
Title and site due diligenceParcel boundaries, access and utility rights, existing liens, and the survey, soil and environmental work the project needs

Ask which item can keep the deal from proceeding even if every other approval comes through. A city may approve the use while a utility still needs to confirm where you can connect. Get the utility’s schedule and the cost of work it requires. If you must build a different access road or buy off-site rights, get a price and see who will own and maintain them. That work can move both the start date and the amount of cash needed.

If early work is allowed, match the exact permit to the portion the lender will fund. A grading or foundation permit can let a contractor start a defined scope. Ask what other approvals are needed before committing to the rest of the job. The City of Hayward, for example, describes phased approvals that permit work on a specific portion before the main building permit, with the risk of design changes still on the applicant. Hayward’s phased permit process

Worked example with a $2.4M land purchase

A developer wants to buy a $2.4M site for apartments and expects to close the construction loan in six months. The seller wants to close now. Assume a $1.44M land loan at 10% annual interest with interest-only payments and no principal reductions before payoff. This is a model for testing timing and cash. The land loan matures in month nine.

What needs fundingModel amount
Sponsor’s share of the purchase price$2.4M − $1.44M = $960K
Land closing fees$60K
Sponsor cash at land closing$1.02M
Monthly land loan interest$1.44M × 10% ÷ 12 = $12K
Monthly taxes, insurance and site upkeep$5K
Planned design and approvals paid before construction$180K

The monthly cost to hold the site is $17K. Six months takes $102K. Add the $180K of design and approvals to the $1.02M needed for land closing and $102K of carry. The developer needs $1,302,000 in cash through the planned start of construction, before a land payoff or costs at the next closing.

What does a six-month delay cost?

Now suppose another round of review moves the construction closing from month six to month twelve. Assume the land lender agrees to extend maturity from month nine to month fifteen for 1% of the outstanding principal. Assume interest and monthly site costs stay the same. The extra six months also bring a second round of design and review expenses.

What the delay addsAmount
Six more months of interest and site carry6 × $17K = $102K
Land loan extension fee1% × $1.44M = $14,400
New design and review costs$50K
Total added cash$166,400
Cash needed before the new construction close$1,302,000 + $166,400 = $1,468,400

Treat the extension as a separate approval unless you have a right to it under the signed loan and can meet its terms. Ask when notice is due, what the lender can charge and whether it wants a new valuation, more equity or a reserve. If no extension is available, the developer in this example has to address the $1.44M principal in month nine, plus any other amounts due. That makes the maturity date at least as important as the estimate for permits.

Get the next decision date from the design team, the local authority and the lender. Put the dates on one line and ask when each would have to move to jeopardize the closing. If a permit takes longer than expected, you want time to discuss an extension while you can still meet its notice deadline. Test the monthly bills with the actual rate and costs in your land loan proposal.

How much of the land loan can the construction loan pay off?

Confirm the amount the construction lender will advance at closing for the land payoff. A construction commitment includes funds that may be held for later work or limited to particular costs. Get the lender’s agreed uses for the first advance. Also request an updated payoff from the land lender with the date it is good through.

Continue the example. Assume the land lender is owed $1.44M at construction closing, with interest paid current, and the new lender can advance $1.1M toward that payoff. The sponsor has to fund the $340K difference. If the developer set aside $1.7M for the site purchase, carry, predevelopment bills and payoff contribution, the six-month plan would leave $398K available for the payoff. That gives a $58K cushion for these modeled uses. After the delay, the same pool leaves $231,600. It is now $108,400 short of the payoff contribution, before other construction closing costs or upcoming bills.

If you are counting on land equity to help qualify, ask how the lender values the site and how it handles the existing debt. Also ask which previously paid design, permit or site costs it can credit. Confirm both the dollar amount of that credit and whether any money will be reimbursed at closing. Use the mortgaged land equity guide to reconcile the land contribution and the payoff.

When would waiting to close make more sense?

Compare the cost to extend site control with the cost to own the site through the same delay. On the contract side, list extension fees and deposits you could lose. Include plans and reports you will pay for in either case. On the ownership side, include interest, taxes, insurance, closing fees and the cost of refinancing. Track any change in the land loan maturity or the price of completing the work. Mark which costs you recover at closing and which you have to fund regardless.

Ask two questions before the next deadline. If the last key approval is denied, can the site support a smaller project or a different use at the land price? If permits come through six months later than planned, can you still close on the construction facility and pay the land debt? Model both before signing a purchase or deposit amendment. If buying now is the only way to retain the site, those answers help you decide how much equity to commit and which loan terms to seek.

How would a smaller approved project affect the purchase?

Ask the architect to price a plan the local rules already allow if the proposed use or unit count still needs review. Use real bids and rents for that smaller plan. Some costs, such as the access road or utility connection, can stay the same with fewer units. Recheck what you can borrow and what income the completed building can earn. Have the team identify which design or permit costs you would have to pay again if the plans change.

Give the lender both sets of numbers and ask which plan it will use while approvals are pending. If you would sell the site as your backup, estimate how much time a buyer needs and what it might pay for a property at that stage. Compare net sale proceeds with the land loan payoff and selling costs. Decide which outcome you can carry before choosing a purchase date or a land loan term.

For a project where the first building can open independently, ask the team to price a smaller first scope. Verify which approval changes it would need and what site improvements it still has to fund. Financing Phase 1 on its own

What should you send for an early site financing review?

Start with the address, purchase price, intended project and your closing deadline. Be specific about what needs to fund now and when you expect to need construction money. Explain what stays outstanding if you buy before permits.

  • Site control. Include the purchase agreement or option, the next deadline, deposit terms, access rights and any extension you can exercise.
  • Approval status. Send the plans, decisions or permits you have, with their dates. Identify the next approval and what could hold it up.
  • Land and carry budget. Show purchase, loan proceeds, fees, monthly interest and site expenses, and predevelopment costs. Run the same schedule with a longer wait.
  • Construction plan. Share the current scope and budget, how much debt you expect to need and the conditions for a first advance. If there is a land loan, include the maturity and payoff plan.

If you have a site and a near-term deadline, request a commercial financing review. Put the deposit or closing date first and say whether you need land-only financing or a facility that will also fund construction. If you are still pricing approvals, bids and draws, start with the construction readiness checklist. For a request focused on streets, utilities and finished lots, see acquisition and development loans.

Frequently asked questions

Can I buy a development site before the building permits are issued?
Yes, if you can close under the purchase agreement and fund the acquisition. A land loan or the land advance of a construction loan may be available. Confirm how you will pay for design, approvals and holding costs until construction funds are available.
Can my construction loan close while permits are pending?
Some lenders may fund a land purchase before all building permits are issued. Start by asking what can fund at closing and which approvals, bids or other conditions must be met for later construction draws. Get those milestones and deadlines in writing.
Is zoning approval the same as a building permit?
Zoning and land-use approvals address the use and what can be built on a site. A building permit authorizes work within an approved scope. Check the local process for the land use, site and building approvals that apply, along with the dates you need them.
How do I budget for a permit delay after buying land?
Multiply the extra months by interest, taxes, insurance and other holding costs. Add new design or review costs and any extension fees that apply. Confirm when the loan matures and how much cash would be needed to repay it if the construction loan is late.
Can a construction loan pay off my land acquisition loan later?
It may if the construction lender permits that use. Compare the dated land payoff with the portion of the new loan it will advance at closing. Show how you will fund the difference, any closing costs and payments due before the first construction draw.

Ready to fund your next deal?

Get pre-qualified in minutes. Speak with a lending specialist or submit your scenario online.

Or call (833) 264-7776

FREE INVESTOR RESOURCE

Unlock your download

Submit your email to download your results. Your deal inputs stay in this browser.

Submit your email to access this free resource. Privacy policy.