Preleased Office Construction Loans

Compare build-to-suit office construction financing with a signed tenant. Plan landlord work, rent commencement, delay reserves and the permanent exit.

Updated

A signed tenant can help an investor qualify for ground-up office construction financing. Banks and private commercial lenders still need to see who pays the rent, what has to be delivered before it starts and how the sponsor will carry the project if delivery slips. Bring the executed lease and the budget it creates to the first conversation.

Office delivery delay calculator

Estimate the cash a late delivery takes out of your reserve and the rent it moves to a later date.

Delivery and reserve assumptions

Estimated results

Added carrying costs
$195,000
Cash needed beyond the reserve
$45,000
Rent receipts deferred
$180,000

How the estimate adds up
  • Assume rent moves back by the entered months. Deferred receipts are shown separately from costs. Check whether lease remedies, rent credits or extra contractor costs change the cash forecast.

Compare lender options · Price a delivery delay · Prepare your request

Who lends on preleased office construction?

Build-to-suit means the project is designed or finished for a particular occupant. For a developer leasing the building to a third-party business, start with commercial construction lenders who will consider that tenant and property. Ask whether they review your office subtype, location, loan amount and stage before you assemble a full package.

Financing conversationFirst questions to ask
Bank commercial construction deskWill the bank consider this tenant, office use and size? What will it need from the sponsor and guarantors?
Private commercial lenderCan the lender work with the actual draw and rent start dates? What cash will be needed up front or held in reserve?
Bank and Certified Development Company for an eligible owner-userWill the operating business and its proposed use of the building meet SBA requirements? How would the construction period be funded?

For a project without a tenant, explain how you would carry it through construction and leasing. A lender may have a separate policy for speculative office. Request a decision on preleasing before paying for third-party work. Ask how the lender measures the lease commitment and what it would need by closing or the first draw. The OCC handbook describes construction feasibility, preleasing and draw controls in bank lending. OCC commercial real estate lending handbook

For a wider comparison of sources, see the commercial construction lender guide. If the building already exists and the work is an acquisition, renovation or lease-up, see the office bridge financing guide.

What will the lender check about the tenant?

Start with the entity shown on the lease and any party that has signed a guaranty. If the tenant operates under a familiar name, identify the company that actually owes the rent. For example, a clinic may use a health system brand while a separate practice entity is responsible for its lease. A lender may ask for financial information on the tenant and any guarantor.

Show the business that will operate here. A lender may review its ability to open, stay open and pay through the term. Explain what is still needed for the tenant to move in. For a medical office, those items might include utilities for equipment, special build-out, a plan for approvals and the tenant’s own move-in schedule. Get dates from the people responsible for each item.

If discussions are at the letter-of-intent stage, show the proposed rent, term and work. Flag terms still in negotiation and when the parties expect to sign. Ask whether the lender can start a review or give preliminary feedback at that stage. If a loan approval or draw requires an executed lease, ask how to build that condition into the schedule.

Consider the building’s next user as well. A single tenant can support all the rent at opening, and the same building can lose all that rent when the tenant leaves. Explain which improvements would work for a replacement tenant and which would need to be changed. If the space serves a narrow medical use, include the time and cost to adapt it.

What if only part of the office is preleased?

If one tenant signs for part of a building, give the lender a lease plan and a full building budget. For instance, a separate 20,000-square-foot project with one lease for 12,000 square feet is 60% preleased by area. The lender will still need to understand the cost of building all 20,000 square feet, the rent expected from the signed tenant and the cash needed while the other space is empty.

Show which costs must be incurred for the signed tenant to open and which can wait. A second suite may have its own work, leasing and timing. Shared structure, power and access can still come due on day one. Ask the lender what percentage of the area or income it considers leased and whether the fit changes if you defer part of the work.

Run a repayment case using the signed tenant and the full owner’s expense budget, including costs attributable to vacant space. Give the lender a separate case if the remaining suites lease. Ask what it would need to count income from those suites. This approach can also show where new equity or a revised construction phase would be needed if leasing takes longer.

When does rent actually start under the lease?

Put the lease dates beside the construction schedule. Start with the date you must deliver the space. Then show when the tenant gets access, when landlord work is due, what must be inspected and when rent begins. For each date, identify who provides the evidence. A delivery certificate or tenant acceptance letter may matter as much as the expected end date in a contractor’s bid.

Read the rent provision with the exhibits. For example, a tenant might take access early to install equipment and begin paying after the landlord finishes specified work. A lease may also give a period of free rent or provide a remedy if delivery misses a certain date. Ask counsel to review the relevant clauses and tell your lender when a change to the lease or a written extension is needed.

Keep the contract dates and your forecast visible separately. If the contractor forecasts an opening in October and the lease has a delivery deadline in September, price the gap and identify the next decision. Ask when the tenant must be notified and what it would take to change the schedule. The lender needs to see the cash and lease consequences before the project is relying on either date.

How much would a three-month office delivery delay cost?

Assume an illustrative 20,000-square-foot medical office with an executed 10-year lease. Rent begins after delivery under the lease. The modeled cost of interest, taxes, insurance and other carry during an additional month is $65K. Construction finishes three months later than planned.

Delay checkIllustrative result
Added carryThree months × $65K is $195K
Unallocated reserve still available$150K
Added cash needed to cover carry$45K
Rent expected later at $60K per month$180K of scheduled receipts are delayed in the illustration

The three-month lag puts another $195K of cost in the forecast. The $180K is rent that would arrive later. Show both in the monthly cash schedule so you can see when cash is due and when income starts. If the lease changes the rent, the term or the tenant’s right to walk away, update the scenario for those actual provisions.

Before signing financing terms, ask what the reserve is allowed to pay. The lender may hold some money for interest, inspections, tenant work or other approved uses. Confirm how the reserve can be drawn and when it would need a top-up. Price any extra contractor charges, rent credits or operating costs that the basic delay estimate leaves open. Use the construction draw and interest calculator to estimate how a longer build changes interest on the funds advanced.

What belongs in the landlord work and draw budget?

Lay out the shell, base building systems, work the landlord is required to finish and costs the tenant pays. Get a dated bid for each item that affects delivery. An allowance, such as money the landlord agrees to reimburse for tenant work, can have a payment date and evidence requirements of its own. Record who approves changes and when the expenses can be reimbursed.

Suppose the modeled lease includes a $900K build-out allowance. An equipment supplier needs a $250K deposit before the next lender inspection. You have $140K available for that payment after other planned bills. The resulting $110K timing gap is separate from the cost of the equipment, which belongs in the project budget once. Check whether the lender would permit an earlier or direct payment, whether the tenant can pay up front under the lease, or whether the sponsor will supply cash.

Compare the contractor’s draw plan with the lease milestone schedule. A lender could require an inspection and invoices before an advance. The tenant might need to order services or equipment well before that point. Put the payment dates, expected draw dates and conditions on the same calendar. Explain long-lead items and who will bear the cost if an order has to change.

On a phased build, show which work is needed for each part of the space to open. Confirm whether the building authority and lease allow early access or partial use. A separate suite might still need common power, fire protection or an access route completed before it can be occupied. If the lease starts rent by phase, ask the lender what proof it needs for each part.

Can the lease support the permanent payoff?

Check the expected permanent loan before deciding which construction loan to sign. Start with rent the tenant would actually pay and the operating expenses the landlord would bear. Review the lease for reimbursements, caps and expenses that fall to the owner. Confirm what expenses the exit lender will deduct and what collection history it needs.

In the office illustration, assume $60K per month of base rent once payments begin. That is $720K annually before property expenses and other adjustments. Suppose annual operating expenses borne by the owner are $180K, giving $540K of net operating income. At an assumed 7.5% cap rate, that suggests a $7.2M estimated value. A modeled 65% loan-to-value limit supports $4.68M in gross refinance proceeds.

Against an illustrative $5M construction payoff, that leaves a $320K gap before refinance expenses. Run the income coverage test as well. It compares annual net operating income with the annual payments the new loan would require. A lender may offer less if the cash flow cannot support the requested payment. Use the construction exit calculator to put your own valuation and debt-service assumptions side by side.

Ask what lease term will be left at the planned refinance date and whether the lender will use contracted or collected rent. Review termination rights and rent adjustments that could change the forecast. If you plan to sell, compare the net sale proceeds after costs and model an extra period to market the building. Match the original construction term to the time needed to deliver, collect rent and complete the exit.

Match the refinance timeline to the tenant’s opening schedule before you accept a construction maturity date. Allow time to provide the lender with the completed lease obligations and the payments it wants to see. If the first rent arrives close to maturity, ask about conditions for extending the loan and put the notice date on your calendar. A lease you can show during initial underwriting may still need a signed acceptance or a rent ledger later.

What if your own business will occupy the building?

If you are building an office or clinic your operating business will use, explore owner-occupied commercial construction financing. Eligibility can depend on the business, use of the property and the portion it will occupy. Ask the lender and Certified Development Company what space can qualify and how the facility would be funded during the construction period. SBA 504 loan overview · Owner-user SBA construction guide

If you are building a space to rent to a separate business, send the lease and tenant information under a commercial construction review. A project with a mix of owner use and third-party tenants should show the area intended for each occupant. Explain how much of the budget serves each use. That gives the lender the facts it needs to determine which financing pathway to review.

What should you send for an office construction review?

Start with the address, office use, rentable area, sponsor, site control, total development budget, loan requested and closing deadline. Give the lender the executed lease with its exhibits, amendments and any guaranty. Identify the tenants expected to open and which license, permits, landlord work or tenant work they still need.

Include a dated construction and lease schedule showing approval, the first draw, delivery milestones and the first expected rent collection. Add the contractor’s bid, sources and uses, sponsor equity, landlord allowances and any reserve for delays. Show what the loan should repay at closing and which advances should remain available for the work. End with the proposed refinance or sale and the gap you found under a delay scenario.

If a condition is still open, say which party can resolve it and by when. Useful examples include a final tenant signature, an approved utility plan, the release of an existing land loan or an allowance that will be billed after delivery. Give the reviewing team a chance to flag conditions early, while there is still time to change the scope or timing.

Request a commercial construction review with the lease, loan amount and dates that drive the deal. If your business will occupy the space, start with the owner-occupied SBA construction guide. Brokers can submit a client project through the broker portal.

Frequently asked questions

Who provides ground-up office construction loans with a signed tenant?
Start with bank commercial construction desks or private commercial real estate lenders that consider your location, loan size and office subtype. A signed lease can support a review. Expect questions about the tenant's credit, lease obligations, delivery schedule, sponsor cash and permanent exit.
Will a lender use a letter of intent instead of an executed lease?
A letter of intent can help a lender understand the proposed tenant and economics. Each lender decides whether it requires a signed lease before approval, closing or particular draws. Identify which business terms and signatures are still open.
What happens to financing if rent commencement is delayed?
Estimate the added monthly carry through the revised start of rent, then compare it with available reserves. Check the lease for delivery dates, remedies and extension rights. Give the lender the revised construction, payment and occupancy schedule.
Can I use SBA 504 financing to build my own medical office?
Eligible businesses may explore SBA 504 financing for construction of space they will occupy. A lender and Certified Development Company can confirm business and occupancy eligibility and how the construction period would be funded.
What should I send for build-to-suit office financing?
Share the site, loan amount, development budget, permits, signed lease and exhibits, tenant and guarantor information, landlord work, draw schedule, rent start and repayment plan. Point out any timing gaps or terms still open.

Ready to fund your next deal?

Get pre-qualified in minutes. Speak with a lending specialist or submit your scenario online.

Or call (833) 264-7776

FREE INVESTOR RESOURCE

Unlock your download

Submit your email to download your results. Your deal inputs stay in this browser.

Submit your email to access this free resource. Privacy policy.