    03 / Follow the funding

    The commitment is only the beginning.

    See when loan dollars reach the project, how a funded balance creates interest, and what a slower schedule could cost.

    Use the calculator 6 minute guide · Interactive tool

    Separate commitment, advances and available cash

    A commitment is the total facility contemplated by the agreement. An advance is money funded under that agreement. The two amounts need not be the same on closing day. If a hypothetical $1.8 million commitment begins with a $300,000 advance, $1.5 million remains undrawn before any later activity. That remaining amount is not automatically available to spend immediately.

    Ask what must happen before each advance, who submits the request, and how long review and payment could take. Maintain a project calendar with invoice dates, draw submissions, inspections and expected disbursements. A contractor’s payment deadline and the lender’s draw review are separate events.

    Make the draw request easy to reconcile

    A useful request connects each claimed expense to a budget line and an evidence item. Keep the original budget, approved changes, previously funded amounts, current request and remaining cost to finish visible together. The NCUA construction guide describes draw reconciliation, inspection and final-funding controls for credit unions. Your transaction’s documents determine the actual requirements.

    An inspection can support the funding review, but it does not replace your own accounting or guarantee construction quality. Ask how stored materials, deposits, disputed invoices and retainage will be handled. Retainage is an amount held back under the applicable arrangement; use the negotiated amount rather than assuming a universal percentage.

    Estimate interest on a visible schedule

    The estimator uses a simple monthly convention: opening principal plus half of that month’s advance, multiplied by the annual rate divided by twelve. It assumes each advance occurs halfway through the month. For a $300,000 opening balance, a $100,000 advance and a 10% annual rate, estimated interest is $2,916.67 for that month.

    The following month opens at $400,000 because this model treats interest as paid separately. It does not add interest to principal. Enter each month’s advance directly, including zero for a month without funding. The tool checks that total principal advances do not exceed the entered commitment. Its chart shows the modeled funded balance over time.

    Actual loan calculations can use specific funding dates, day-count conventions, changing rates, additional fees and financed interest. If interest is advanced from the loan, those advances can consume commitment and affect future interest. This simplified model does not solve that circular calculation. Its separate reserve input is only an amount available to cover modeled interest, not extra funding added to the loan.

    Give delays a dollar amount

    The delay scenario holds the completed base schedule’s ending principal constant for the added months, with no new draws or principal repayments. At $1.5 million and 10% annual interest, three added months create $37,500 of extra interest. If other carrying costs are $2,500 per month, the combined incremental burden is $45,000.

    Those are arithmetic assumptions, not an extension quote. The scenario excludes extension fees and does not establish a right to extend. Compare the delayed payoff date with the actual maturity date, then ask what happens if they no longer align.

    Reconcile the interest allowance

    The OCC commercial real estate handbook explains that reserves must be evaluated against disbursement timing, interest rates and completion or lease-up assumptions. Use the tool’s base and delayed results to revisit your allowance. If modeled interest exceeds the entered reserve, identify the cash shortfall explicitly. A remaining reserve balance is not evidence that the overall construction budget is adequate.

    Put it into practice

    Draw & delay estimator

    Hypothetical starting values. Edit the assumptions, calculate, then explore a different case.

    Calculator assumptions
    Monthly construction advances

    Enter principal advances only. Initial advance is entered above; interest is paid separately.

    Your scenario

    Results, explained.

    Inputs are processed in your browser. These results are educational estimates, not an eligibility or financing decision.

    Keep building your plan

    Planning the exit: refinance or unit sales

    A finished building is a milestone. A credible repayment plan connects that milestone to the cash needed to retire construction debt.

    Continue to the next guide ← Previous: Budgets & equity

    Prepared November 2, 2026 · Published by Jaken Finance Group. General references are linked beside the relevant discussion; bank and credit-union guidance does not establish this product’s terms. Product parameters are from the supplied brief and have not been independently confirmed as a current offer.