Skip to main content
JFG

Search

    Press ⌘K or Ctrl+K

    SEE YOUR RATE

    Example: Paradise Valley Luxury Scrape Construction

    Example: Paradise Valley luxury scrape — $1.42M all-in, 75% LTARV bind, Scottsdale custom comps, 17-month vertical. Jaken Finance Group construction stack.

    Deal snapshot

    Location Paradise Valley, Arizona (Scottsdale fringe) — composite example
    Property type Custom SFR scrape (luxury spec)
    Loan type Ground-up construction — milestone draws
    Loan amount $1.05M (75% of $1.40M as-completed)
    Close time 14 business days from complete construction package

    Problem — land-heavy file, thin spread, wrong comps almost blew it

    A repeat Arizona operator controlled a 1979 block ranch on a Paradise Valley lot north of Camelback and ran two columns: $285,000 gut versus scrape and custom vertical. Gut math showed $890,000 all-in and $1.05 million ARV — thin. Scrape math showed $1.42 million all-in and $1.40 million as-completed only after Paradise Valley comps replaced Arcadia tract imports.

    The sponsor’s first lender quoted 90% LTC on a one-pager. Qualified luxury construction up to $2.5M can reach 100% LTC — but the value cap said 75% LTARV = $1.05 million on the corrected as-completed. Spread lives in submarket discipline and calendar, not a lower LTC ceiling on luxury.

    Product pages: luxury new construction · spec home construction (national box) · Gut alternative: luxury fix and flip · Calculator: luxury spec LTC.

    Property snapshot

    LineAmount
    Land / existing structure acquisition$585,000
    Demolition and site prep$28,000
    Vertical hard (3,680 sf × ~$158/sf)$580,000
    Pool, hardscape, landscape$94,000
    Soft costs, plans, engineering$52,000
    Permits, fees$12,500
    Contingency (~11% of hard)$75,000
    Vertical stack subtotal~$1,426,500
    Interest + marketing reserve$122,000
    All-in~$1,548,500
    As-completed (Paradise Valley custom solds)$1,400,000
    75% LTARV$1,050,000
    100% LTC on $1.42M vertical stack$1,420,000 (LTARV binds first)
    Loan in example$1,050,000 (LTARV binds)
    Sponsor equity + reserve beyond loan~$498,500 in example math

    Note: example compresses some soft lines for readability — sponsor had land equity and liquidity for LTARV gap before LOI. Files without gap cash do not start.

    Challenge

    Three failures common on Arizona luxury scrape files:

    Arcadia comp import. Production tract $680K–$740K solds do not value Paradise Valley custom. ARV fantasy adds $100K–$150K until appraiser cuts.

    Six-month IO reserve on seventeen-month build. Paradise Valley custom runs 15–18 months vertical plus 90-day jumbo buyer seasonality in shoulder season.

    City vs town confusion. This lot was town of Paradise Valley — not city of Phoenix. Sponsor nearly modeled Phoenix impact fees from a wrong jurisdiction lookup.

    Monsoon during framing. August storm hit before dry-in. $16,000 sponsor deductible — reserved, not borrowed.

    Solution — 100% LTC available, 75% LTARV funded

    Jaken Finance Group construction box in example: 8.99%–13.5% interest-only, 14 business days close on complete package. Funded $1,050,000 — the lower of LTC and LTARV, under the $2.5M program ceiling.

    Draw gates

    GateWorkNotes
    1Demo, utilities, foundationNo finish front-load
    2Framing / dry-inMonsoon claim processed before insulation
    3MEP roughTown of Paradise Valley inspection sequence
    4Drywall / exteriorPool shell parallel
    5Finish / COStaging line separate from draw

    Rate in carry model: 11% IO on rising balance. Change orders on millwork stayed inside 11% contingency.

    Result — timeline in the example

    MilestoneTiming
    Complete package inDay 0
    Close / first drawDay 14
    Foundation / Gate 1Week 9
    Dry-in / Gate 2Month 6
    COMonth 17
    ListMonth 18
    ContractMonth 20
    Close saleMonth 21

    List price: $1,449,000 · Sale: $1,385,000 net of 8% costs → thin spread after $122K carry — margin was buying land $52K better and avoiding $135K ARV overstatement, not coupon heroics.

    If DOM slipped past day 90, next step in file was luxury bridge — not a $100K price cut. Exit playbook: luxury spec home exit at 60–120 DOM.

    Takeaway

    Paradise Valley luxury scrape is a value-cap and submarket product that uses draws. Scottsdale-fenced comps, town permit path, monsoon reserve, and 17-month calendar beat a 7.75% teaser on the wrong machine.

    Compare: volume flip vs jumbo construction · jumbo hard money over $1M.

    New construction application · Submit scenario · (833) 264-7776

    What the first term sheet got wrong

    Shop A offered 90% LTC without Paradise Valley comps. Shop B was a six-month flip note. Neither matched scrape vertical. The example closed construction because plans, submarket comps, and reserve were complete — not because spread was effortless.

    When this example does not apply

    Comp mistakes — how Arcadia tract solds inflated ARV by $135,000

    The sponsor’s first pro forma used three solds from Arcadia and south Phoenix production neighborhoods. On paper they looked close: similar square footage, recent close dates, and list prices in the $680,000–$740,000 range. The spreadsheet averaged them, added a $620/sf premium for Paradise Valley, and landed at $1,535,000 as-completed.

    The listing agent and appraiser rejected every comp. Paradise Valley custom buyers do not shop Arcadia tract inventory. They compare Mummy Mountain, Lincoln Drive, and Cheney Drive corridors where lot sizes run 0.4–0.8 acres, setbacks differ, and finish levels include custom millwork, site walls, and pool packages that tract builders never deliver.

    Comp mistakeWhat the sponsor usedWhat underwriters acceptedARV impact
    GeographyArcadia / south Phoenix tractParadise Valley + north Scottsdale custom only−$85,000
    Finish levelProduction-grade tract interiorCustom spec with designer package−$32,000
    Lot utilitySmaller infill without viewsView corridor + larger pad−$18,000
    Total correction$1,535,000 fantasy$1,400,000 defensible−$135,000

    After correction, 75% LTARV dropped from a theoretical $1,151,000 to $1,050,000 — and the sponsor’s equity gap widened by $101,000 before vertical started. That is why Jaken Finance Group asks for submarket-fenced solds in the intake packet, not a radius search from Google Maps.

    Rules that saved the file: fence comps to the same town or custom submarket; match above-grade sf within 15%; require two solds and one pending above $900,000; reject any comp with HOA tract architecture when the subject is custom scrape.

    Draw schedule — milestone dollars, retainage, and inspection sequence

    Construction funded $1,050,000 in five gates with 10% retainage held until certificate of occupancy. No finish materials were front-loaded. Each draw required GC invoice, lien waiver, and town inspection sign-off before wire.

    Gate% of loanDraw amountWork completedRetainage heldCumulative drawn
    Close / Gate 015%$157,500Land equity credited; demo mobilization$15,750$157,500
    Gate 120%$210,000Demo, utilities, foundation pass$21,000$367,500
    Gate 225%$262,500Framing, roof dry-in, windows$26,250$630,000
    Gate 320%$210,000MEP rough, insulation, drywall hang$21,000$840,000
    Gate 415%$157,500Exterior, pool shell, cabinets$15,750$997,500
    Gate 5 / CO5%$52,500Finish, landscape, CO, staging$5,250$1,050,000
    Retainage release$105,000Final lien waiver + COReleased at CO$1,050,000

    Average drawn balance for IO modeling was ~$525,000 through month 10, rising to ~$945,000 months 14–17. At 11% interest-only, monthly carry stepped from ~$4,800 early to ~$8,700 at peak — which is why a six-month IO reserve would have failed at month 14.

    Monsoon damage at Gate 2 triggered a $16,000 sponsor deductible before insulation. The draw paused eleven days for dry-out and re-inspection — calendar slack lived in contingency, not a supplemental loan request.

    Town of Paradise Valley inspections ran foundation → rough frame → MEP rough → insulation → final. Pool shell pulled in parallel at Gate 4 so landscape did not push CO past the 17-month model.

    Extended timeline — pre-close through sale close

    PhaseWeek / monthEventCash / loan event
    Pre-closeWeek −4 to 0Comp correction, plans, GC contract, LOISponsor liquidity verified for LTARV gap
    CloseDay 14First draw + interest reserve funded$157,500 drawn; IO reserve $122,000 escrowed
    VerticalMonth 1–6Demo through dry-inGates 1–2; balance rises
    VerticalMonth 7–12MEP, drywall, exteriorGates 3–4
    VerticalMonth 13–17Finish, pool, landscapeGate 5; retainage held
    CO + listMonth 18Certificate of occupancy; MLS liveStaging $18,000 from sponsor reserve
    MarketingMonth 18–20Showings; one failed jumbo buyerIO from reserve; no price cut yet
    ContractMonth 20Accepted offer $1,385,000Bridge not needed
    Sale closeMonth 21Net after 8% costsConstruction payoff from proceeds

    If dry-in had slipped six weeks from monsoon repeat, CO would have hit month 18.5 — still inside the 21-month sale model but eating ~$26,000 extra IO. The sponsor held $75,000 contingency for exactly that.

    Bridge exit math — if DOM slipped past day 90

    The file modeled retail exit first. If DOM reached day 90 with no contract, the next step was luxury bridge while listed — not a $100,000 panic cut.

    Bridge sizing in the example used appraised value $1,380,000 (list $1,449,000 with 5% showing cushion) and 65%–70% LTV on listed collateral:

    LineAmount
    Appraised value at day 90$1,380,000
    Bridge at 68% LTV$938,400
    Construction payoff$1,050,000
    Sponsor cash-in at bridge~$111,600 plus closing costs
    Bridge rate (IO)10.25% example
    Monthly IO on $938,400~$8,018
    Target DOM extension90 days
    Bridge IO cost (3 months)~$24,054

    Bridge did not erase the LTARV equity gap — it bought time for the jumbo buyer pool without training the market on a headline slash. Payoff still came from sale proceeds. Jaken Finance Group sizes listed bridge on appraisal + DOM plan, not stale list price.

    Compare bridge IO to a 10% price cut at day 45:

    Exit pathList / saleEst. net (8% costs)Spread vs $1.42M vertical stack
    Hold list + bridge 90 days$1,449,000 → $1,385,000 sale~$1,274,000Thin; bridge IO ~$24K
    10% cut at day 45$1,304,000 → faster sale~$1,200,000~$220K spread gone
    4% cut at day 90 + bridge$1,391,000 → $1,340,000 sale~$1,233,000Disciplined; preserves buyer psychology

    Price-cut cadence — what the listing plan said

    Luxury specs punish panic. The agent and sponsor agreed in writing before CO:

    DOM windowActionRationale
    Day 0–60Staging refresh, photography, broker open — no price changeJumbo buyers need multiple visits; early cuts signal distress
    Day 60–90Re-run Paradise Valley solds; if list-to-comp spread >7%, plan one 3%–4% reductionComps in this example supported $1,340,000–$1,380,000 at list
    Day 90–120Second 3%–4% cut only if showings flat and fresh solds moved downTwo small cuts beat one 12% headline
    Day 120+Bridge while listed or DSCR hold conversationRetail seasonality, not coupon shopping

    In the example, no cut was needed — contract at month 20 with $64,000 list-to-sale delta (4.4%). The cadence still mattered because it stopped the sponsor from cutting $100,000 at day 50 when one buyer lost jumbo approval.

    Full exit playbook: luxury spec home exit at 60–120 DOM.

    DSCR fallback — if the jumbo buyer pool never showed

    Business-purpose hold was the third lane. Paradise Valley custom can rent to corporate executive tenants at $8,500–$11,000/month — but DSCR sizes on documented rent, not STR fantasy.

    InputConservativeAggressive (clean file)
    Appraised value$1,380,000$1,400,000
    LTV70%75%
    Loan proceeds$966,000$1,050,000
    Rate (amortizing)7.25%6.85%
    Market rent$9,200/month$10,500/month
    PITIA + reserve~$8,100/month~$8,900/month
    DSCR~1.14~1.18

    Construction balance $1,050,000 at 75% LTV on $1,400,000 equals full payoff — zero cash-out. At 70% LTV, the sponsor needed ~$84,000 cash-in plus closing costs. The hold had to work on cash flow, not equity extraction.

    That is why presale marketing and luxury bridge timing matter before pivoting to DSCR. Jaken Finance Group underwrites DSCR on rent roll or market rent comps in the same submarket — not a Zillow estimate from Arcadia.

    Repeat operator with two prior Arizona flips and a GC who had delivered Paradise Valley custom — not first-file ranch experience applied to scrape.

    Example deal math on investor real estate. Rates, terms, and conditions apply only to qualified borrowers and may change without notice. Jaken Finance Group does not finance owner-occupied housing.

    Frequently asked questions

    Why did 75% as-completed value bind instead of 100% LTC?
    All-in cost was about $1.42 million. As-completed value from Paradise Valley and north Scottsdale custom solds was $1.40 million. Seventy-five percent of $1.40 million is $1.05 million — lower than 100% of cost at $1.42 million. Qualified luxury construction up to $2.5M can reach 100% LTC, but the facility funds the lower number.
    What mistake almost killed the ARV in this example?
    Initial pro forma used two Phoenix production tract solds in Arcadia. Appraiser and listing agent rejected them — Paradise Valley custom comps from the Mummy Mountain and Lincoln Drive corridors only. ARV dropped $135,000 before vertical started.
    How long was carry modeled?
    Seventeen months vertical plus ninety days marketing at 11% interest-only on a rising drawn balance — about $122,000 total IO in the example, funded from reserve not sponsor panic at month fourteen.
    Is this the same as a Scottsdale condo flip?
    No. Condo flips use acquisition-plus-rehab on existing stock with shorter terms. This example is demo, vertical, milestone draws, and owner-occupant resale exit above $900,000 on a fee-simple lot.
    Where do I send a similar Arizona luxury file?
    Plans, budget, GC contract, submarket-fenced comps, and exit narrative — new construction application or submit scenario. Gut-only rehab without demo uses luxury fix and flip guidance instead.

    Fund your next deal with Jaken Finance Group

    Hard money, DSCR, and bridge loans for real estate investors nationwide.

    Or call (833) 264-7776