Skip to main content
JFG

Search

    Press ⌘K or Ctrl+K

    SEE YOUR RATE

    Blog

    Ground-Up Construction Loan Draw Schedule Explained

    By Jason Taken · Principal

    How investor construction draws work — inspections, release timing, and interest on undrawn balance. Avoid GC idle time.

    Construction draws release funds after third-party inspection at milestones — typically 8–12 draws on a 12-month build. Interest often accrues on the full loan commitment, including undrawn holdback.

    Submit clean draw packages early. How to submit a scope of work · new construction loans.

    Typical draw milestones — 12-month SFR build

    Draw #Milestone% of budget
    1Foundation / footings10–15%
    2Framing / roof dry-in20–25%
    3Plumbing / electrical rough15–20%
    4HVAC / insulation10%
    5Drywall10%
    6Cabinets / trim10%
    7Final MEP / fixtures10%
    8CO / punch list5–10%

    Each draw requires third-party inspection — submit invoices, lien waivers, and photos 48 hours before inspection date.

    Common draw delays — and fixes

    DelayFix
    Incomplete lien waiversCollect from subs at each draw
    Work ahead of scheduleLender won’t fund uninspected work
    GC idle between drawsStagger subs; pre-order long-lead items
    Change orders without approvalSubmit CO to lender before work

    Jaken Finance Group construction: 8.99%–13.5% IO, up to 100% LTC qualified, 75% LTARV. How to submit SOW · new construction hub

    Interest on undrawn balance — budget example

    $420K commitment, 12-month build, 10.75% IO

    MonthDrawnUndrawnIO charge base (full commitment)
    1$63K$357K$420K → ~$3,763/mo
    6$252K$168K$420K → ~$3,763/mo
    12$420K$0$420K → ~$3,763/mo

    You pay on full commitment even when undrawn — verify on term sheet from Jaken Finance Group.

    GC coordination for smooth draws

    1. Submit draw request 5 days before needed wire
    2. Include signed lien waivers from all subs paid prior draw
    3. Schedule inspection before ordering next material batch
    4. Never get more than one draw ahead of inspected work

    Spec home financing · SOW submission

    Lien waiver chain — non-negotiable

    Every draw package needs unconditional lien waivers from:

    • General contractor
    • Every subcontractor paid from prior draw
    • Material suppliers above state threshold

    Missing waivers delay draws 5–10 business days — you still pay IO on full commitment.

    Change orders during construction

    CO sizeLender process
    Under 5% of budgetOften approved in-house
    5%–15%Revised budget + re-inspection
    Over 15%Full re-underwrite of LTARV

    Construction cost guide · Jaken Finance Group 8.99%–13.5% IO

    Retainage — why the final draw is never 100%

    Most construction lenders hold 5%–10% retainage until punch list completion and lien waiver clearance:

    Retainage %On $420K budgetRelease trigger
    5%$21,000Final inspection + CO
    10%$42,000Same + 30-day lien period

    Sponsors who model eight equal draws forget retainage — and run out of cash for landscaping, driveway, and final MEP when the lender will not fund draw 8 at 100%. Budget sponsor cash for retainage gap plus 2 weeks of GC overhead after CO.

    Weather and force majeure — draw timing in cold climates

    Chicago, DC, and Midwest builds lose 30–60 days to frost, concrete cure delays, and roofing temperature minimums:

    SeasonRiskDraw impact
    Nov–Mar (cold)Concrete/foundation delayDraw 1–2 slip 3–6 weeks
    Apr–MayCatch-up framingDraw 2–3 compressed
    SummerOn scheduleNormal cadence

    Extend your construction term sheet for one free extension if breaking ground after October 1 in the Midwest — IO on full commitment continues during weather delays whether or not the GC is on site. Spec home financing covers market selection; this section covers calendar risk on the same product.

    Inspector selection — who signs off on each draw

    Construction lenders use third-party inspectors independent of the GC:

    Inspector typeWhat they verifyTypical fee
    Draw inspectorPercent complete vs budget line$150–$350 per visit
    Structural engineer (if flagged)Foundation, framing$500–$1,200
    MEP inspector (some lenders)Rough-in before drywall$300–$600

    You cannot substitute your GC’s sign-off for the lender inspector — ordering drywall before rough-in inspection passes is the #1 draw rejection on investor builds. Schedule inspections 48 hours before you need the wire; same-day requests rarely fund.

    Spec vs custom build — draw cadence differences

    Build typeDraw countLender comfortCommon delay
    Spec (no buyer)8–12LTARV caps leverageMarket absorption at CO
    Pre-sold custom6–10Higher LTC if contract in fileBuyer selection changes
    Build-to-rent (BTR)10–14DSCR exit modeledLease-up after CO

    Spec builds often front-load framing and dry-in draws (40%–50% of budget by month 4) because lenders want the structure weathertight before releasing finish dollars. Custom builds with a signed contract may release finish draws faster — but change orders from the buyer still trigger re-inspection. Pair this guide with construction-to-DSCR refinance when your exit is hold, not sale.

    Draw package checklist — what the lender expects each time

    Every draw request should include:

    1. Signed draw request form with line-item completion percentages
    2. Invoices matching budget categories (not lump-sum GC invoice)
    3. Unconditional lien waivers from GC and all subs paid on prior draw
    4. Dated photos of completed work (geo-tagged preferred)
    5. Updated schedule showing next milestone date

    Missing any item delays funding 5–10 business days — you pay IO on the full commitment while waiting. Submit packages through the channel your lender specifies; email attachments without a draw number often sit in queue behind complete files.

    Soft costs in draw schedules — permits, fees, and interest reserve

    Ground-up budgets split hard costs (labor and materials) from soft costs (permits, architect, engineering, loan fees). Lenders release soft costs on different schedules:

    Soft costTypical draw timingDocumentation
    Building permit feesDraw 1 or pre-closePaid receipt
    Architect progress billingDraws 2–4Invoice + % complete
    Interest reserveHeld by lenderReleased monthly to pay IO
    Contingency lineLast 5%–10%Change order approval

    Interest reserve held in the loan commitment pays your monthly IO so you do not wire cash during build — verify whether your term sheet includes interest reserve or expects sponsor-funded IO from day one. Missing interest reserve on a 12-month build adds $35K–$45K in sponsor cash need beyond equity injection.

    Ground-up construction draws — tie schedule to exit

    Draw schedules are the operating rhythm of any ground-up investor build — spec, custom, or build-to-rent. Model retainage, weather delay, and inspector lead time before you sign a 12-month term sheet at 8.99%–13.5% IO. Your exit determines how tight the schedule must be: spec-to-sell needs CO aligned with absorption season; build-to-rent needs lease signed before the last retainage release so construction-to-DSCR can pay off the construction balance. New construction loans for investors covers program leverage; this guide covers the monthly mechanics that keep draws funding on time.

    Pre-qualify for construction financing

    Need financing for your next project?

    Talk to a Jaken Finance Group lending specialist about hard money options tailored to your deal.

    Or call (833) 264-7776

    Need the loan program for this strategy?

    See your rate in about 30 seconds, or search for a matching calculator or guide.