Blog
Chicago Rehab Draws: Sworn Statements and Lien Waivers
By Jason Taken · Principal, Jaken Finance Group
Keep Chicago rehab draws moving with clear contractor sworn statements, lien waivers and payment records. Plan the cash needed before each loan release.
Chicago rehab draws need a clear record of the work, the bills and the people still owed money. A contractor’s sworn statement identifies those parties. Lien waivers address their lien rights. Your lender then applies the draw terms in your loan agreement before it releases funds.
The practical risk is simple. Your contractor asks for payment on Friday, but the lender needs a missing supplier document before sending the draw. Payroll, interest and the next delivery still need cash. A finished kitchen does not resolve a disputed bill behind it.
For a Chicago fix-and-flip loan, settle the payment process before closing. Have an Illinois construction attorney review the legal documents. Ask the lender and title team which forms, approvals and payment methods your project requires.
Start with three different questions
Every draw should answer three questions: What work is complete? Who needs payment? Does the requested amount fit the approved budget? Each question needs its own evidence.
| Question | Useful evidence | What it does not establish alone |
|---|---|---|
| What work is finished? | Photos, site visit and completed work list. | Whether every worker and supplier was paid. |
| Who is owed money? | Current contractor statement and supporting bills. | Whether the lender approved the work or cost. |
| What may the lender release? | Approved budget and written draw terms. | Whether the city signed off on required work. |
Keep those reviews separate in your schedule. The city checks work under its permit process. The lender checks the conditions attached to its money. The title team reviews issues that could affect its coverage and the mortgage.
Ask who coordinates those reviews on your deal. A loan officer, draw servicer and title closer may each handle only part of the process. Learn their roles before the first request. See the fix-and-flip draw process for the broader sequence.
What Illinois requires from the contractor
Section 5(a) of the Illinois Mechanics Lien Act requires a written statement under oath or verified by affidavit before contractor payments or advances. It lists parties supplying labor, services, materials and other covered items, with their addresses and amounts due or to become due. The contractor must provide it, and the owner must require it. The subsection excludes merchants and dealers supplying materials only from making these statements. Illinois Mechanics Lien Act, Section 5.
Do not read the section’s owner-occupied heading as a blanket exemption for investment properties. The extra notice in subsection (b) concerns owner-occupied single-family homes; subsection (a) sets out the contractor statement duty. Ask counsel how the Act applies to your contracts and payment structure.
A useful operating habit is to request an updated statement with each payment package. Ask your attorney which version to use and who must sign. Give the contractor that requirement at bid time. It is much harder to introduce a new process when a crew is waiting for money.
A statement, invoice and waiver each do a different job
An invoice asks for payment. A receipt records a payment. A sworn statement identifies work participants and their balances. A lien waiver addresses the signing party’s rights, subject to its wording. Keep all four where the project calls for them.
A progress waiver and a final waiver can cover different amounts or periods. A conditional form may depend on receiving payment; an unconditional form may not. Have counsel review the actual text. Do not choose by the document’s title alone. AIA Contract Documents explains these form types and stresses choosing one suited to the project’s law. AIA guidance on sworn statements and lien waivers.
Consider a $9,000 electrical contract with $6,000 paid. A document covering that payment should not casually become a statement that the entire trade is paid in full. A later approved change also needs to appear in the records. Otherwise, two parties may use the same form to describe different balances.
Likewise, a waiver from the general contractor does not by itself show what happened to the cabinet supplier’s bill. Trace the requested payment to the people and work behind it. Keep each party’s exact legal name consistent across the contract, statement, invoice and payment record.
Build one packet for each draw
Choose a simple name such as “Draw 2, September 18” and keep that name on every file. Include the property address and loan reference. Number each approved budget item so a reviewer can match a bill to the scope without guessing.
| Packet item | What to check before sending |
|---|---|
| Draw request. | Current request, prior releases and remaining budget agree. |
| Contractor statement. | Party names and balances reflect the current work. |
| Bills and payment records. | Each charge matches a budget item and property. |
| Required waivers. | Payee, amount, period and payment status agree. |
| Progress evidence. | Photos show the work requested, with location and date. |
| Permit or inspection records. | Include the approvals required for that stage. |
| Approved changes. | Revised work and costs have written approval. |
Include a short cover note for exceptions. If one cabinet door is delayed, say which item is incomplete and what amount remains. If a supplier changed its business name, provide the link between the old contract and new invoice.
Request only what the evidence supports. Ordering a furnace, delivering it and installing it are three different events. The loan may treat them differently. Follow the agreement rather than assuming that a paid invoice makes the whole line ready for release.
Start with an itemized scope of work. A budget that simply says “rehab: $90,000” makes each later payment harder to review.
Reconcile the budget before requesting funds
Use three running figures for each trade: the approved contract amount, payments already made and the balance still owed. Track approved changes beside the original contract. Do the same for lender releases, which may follow a different schedule.
Suppose a plumbing contract starts at $14,000. An approved $2,000 repair makes the revised total $16,000. Prior payments of $5,000 and a new $4,000 payment leave $7,000 unpaid. If the contractor’s statement shows a $5,000 balance, resolve the $2,000 difference before sending the package.
That difference might be an omitted change, an invoice credit or a payment entered twice. Ask for evidence rather than silently forcing the numbers to agree. Save the correction with the draw it affects.
Also compare remaining funds with the cost to finish. An account can reconcile perfectly while the project is underfunded. If only $20,000 remains available but current bids show $28,000 of unfinished work, the project needs another $8,000. A clean form cannot solve that cash shortage.
Use the Chicago rehab budget guide to organize the scope. Use current bids for your property when deciding what each unfinished task will cost.
Hypothetical Chicago example: the first draw cash gap
Assume an investor buys a vacant Chicago bungalow with an approved $90,000 rehab budget. This is a planning example, not an actual customer file or a loan offer. Assume the lender reimburses eligible completed work and holds back 10% of each approved request until final release.
The investor starts with $35,000 of working cash after closing. The first stage requires $12,000 for labor and $8,000 for installed materials. Both are paid before the lender’s review. The investor also spends $6,000 on a cabinet deposit for a later stage.
| Cash movement | Amount | Cash remaining |
|---|---|---|
| Working cash after closing. | $35,000. | $35,000. |
| Completed labor and installed materials. | Minus $20,000. | $15,000. |
| Deposit for later cabinets. | Minus $6,000. | $9,000. |
| Approved first draw, less 10% withheld. | Plus $18,000. | $27,000. |
The first request is $20,000. Under these assumptions, the lender retains $2,000 and releases $18,000. The cabinet deposit is outside this draw. After reimbursement, $8,000 of the investor’s original cash remains tied up: $6,000 in cabinets and $2,000 withheld.
The lowest balance before the wire is $9,000. If carrying costs and the next deposit need $11,000 before that wire arrives, there is a $2,000 timing gap. The project can have ample total loan funds and still miss a payment.
Resolve this before signing the contractor schedule. Possible discussions include smaller inspectable stages, a later supplier deposit or more working cash. The lender must approve any change affecting its release terms. Do not assume it will advance an extra draw to match an early contractor bill.
Run the full holding period through the fix-and-flip calculator. Keep a separate weekly cash calendar because a total-profit estimate can hide a short cash gap.
When city inspections and draws fall out of sync
A lender’s site visit may show progress while required city approvals remain outstanding. The reverse can also happen: a city inspection passes, but the financial packet still lacks a waiver or invoice. Ask what each approval unlocks.
Before closing walls, confirm the required trade inspections with the professionals responsible for your permits. Put those dates ahead of the next trade’s start. Have the GC tell you when work will be ready, then leave room for corrections.
Avoid scheduling a draw around an assumed inspection date. Use an actual milestone and ask the lender what it needs if the city reschedules. Keep the Chicago permits guide and your permit professional’s instructions beside the construction calendar.
For a property with open cases, identify the exact cure work before setting the first draw. Review Chicago building violations due diligence before agreeing to a completion deadline.
What changes when someone claims unpaid money
Illinois law gives qualifying subcontractors lien rights, subject to the Act. Paying the general contractor does not settle every possible claim by other parties. Section 32 also ties proper contractor payments to the owner’s exercise of rights under the Act. Section 21 and Section 32.
Send any claim or notice to your attorney promptly. Section 24 addresses subcontractor notice, including timing and permitted delivery methods. A letter may matter before a lien appears in a title search. Do not wait for a recorded lien before asking counsel to assess it. Section 24.
Section 27 addresses retaining funds after notice and the treatment of payments. The proper response depends on the claim and project records. Let counsel direct how much to retain, whom to pay and what releases are needed. Section 27.
Your immediate task is to preserve evidence. Save the contract, all versions of the statement, approved changes, invoices, waivers, payment confirmations and messages. Explain the issue to the lender and title team. Ask which portions of a pending draw can proceed while counsel resolves the disputed amount.
Handling contractor changes without losing the record
A replacement GC needs a reliable starting point. Photograph the work, list unfinished items and confirm what materials belong to the project. Record each prior contract balance before accepting the replacement bid. Separate correcting old work from finishing work that was never done.
Ask the lender how it approves a contractor change and a revised budget. Ask your permit professional how the change affects the permit record. If you plan to take over the work, first review acting as your own Chicago contractor.
Do not overwrite the original scope. Keep a dated copy of the old and new budgets with a short explanation for each changed amount. This lets the reviewer see why the cost rose and which source will cover it.
At final draw, reconcile the project again. Confirm how remaining funds, final waivers, unpaid changes and required inspection records will be handled. Keep the complete file for the sale or refinance. The last payment should close the record as well as the work.
Agree on the first draw before closing
Bring the proposed contractor contract, first-stage budget and weekly cash calendar to the loan discussion. Ask who receives requests, which forms are required and what starts the review clock. Confirm treatment of deposits, stored materials, fees and final withheld funds in writing.
Then submit your Chicago flip for review with that plan. A clear first draw gives the loan team something concrete to assess. It also lets you negotiate contractor payment dates around money you can actually access.